10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat.
With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690
Published rate₹1,074.50per Sqm
Rate analysis
10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat.
DSR rate₹1,074.50per Sqm
With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690
Item code
12.17.1
Sub-head
SH 12 · ROOFING
Unit
Sqm
Source row
1062
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for (mud) 10.00sqm.
MATERIAL
Mud Phuska = 1.048 cum.
Wastage 20% = 0.209
Total = 1.257 cum.
0811
Mud (dry)
cum
1.257
₹190.00
₹238.83
Mud mortar for 25 mm thick plaster over phuska
3.18
Rate as per Item Number 3.18 of SH: Mortars
cum
0.263
₹940.55
₹247.36
Bhusa 0.263x35 = 9.20
5% wastage = 0.46
Total = 9.66 Kg. say 10 kg = 0.1 q
0308
Bhusa
quintal
0.1
₹530.00
₹53.00
9999
Cowdung
L.S.
5.33
₹2.27
₹12.10
9999
Mud mortar for gobri leaping
L.S.
8.06
₹2.27
₹18.30
9977
Carriage of bhusa and cowdung
L.S.
2.73
₹2.27
₹6.20
7904
Machine moulded common burnt clay tile bricks of class designation 12.5
1000 Nos
0.38
₹5,200.00
₹1,976.00
2207
Carriage of Brick tiles
1000 Nos
0.38
₹0.00
₹0.00
Cement mortar for grouting 1:3 (1 cement : 3 fine sand)
3.3
Rate as per Item Number 3.3 of SH: Mortars
cum
0.061
₹4,379.05
₹267.12
Integral water proofing compound 2% by weight of cement
1213
Water proofing materials
kilogram
0.006
₹45.00
₹0.27
9999
Sundries
L.S.
6.76
₹2.27
₹15.35
LABOUR
0124
Mason 2nd class
day
1.3
₹816.00
₹1,060.80
0114
Beldar
day
3.75
₹736.00
₹2,760.00
0101
Bhisti
day
1.1
₹816.00
₹897.60
Rate build-up
TOTAL
₹7,552.93
Add 1 % Water charges on "W"
₹75.53
TOTAL
₹7,628.46
Add GST on "X" (multiplying factor 0.2127)
₹1,622.57
TOTAL
₹9,251.03
Add 15% CPOH on "Y"
₹1,387.65
TOTAL
₹10,638.68
Add Cess @ 1% on "Z"
₹106.39
Cost of 10.00 sqm.
₹10,745.07
Cost of 1 Sqm.
₹1,074.51
Say
₹1,074.50
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.