DSR 2023 · SH 12 · ROOFING

CPWD DSR item 12.17.1 rate analysis

10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat. With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690

Published rate₹1,074.50per Sqm
Rate analysis

10cm thick (average) mud phaska of damped brick earth on roofs laid to slope consolidated and plastered with 25 mm thick mud mortar with bhusha @ 35 kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow-dung) and covered with machine moulded tile bricks, grouted with cement mortar 1:3 ( 1 cement : 3 fine sand) mixed with 2% of integral water proofing compound by weight of cement and finished neat.

DSR rate₹1,074.50per Sqm

With machine moulded common burnt clay F.P.S. (non modular) brick tiles of class designation 12.5, conforming to IS 2690

Item code
12.17.1
Sub-head
SH 12 · ROOFING
Unit
Sqm
Source row
1062

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for (mud) 10.00sqm.
MATERIAL
Mud Phuska = 1.048 cum.
Wastage 20% = 0.209
Total = 1.257 cum.
0811 Mud (dry) cum 1.257 ₹190.00 ₹238.83
Mud mortar for 25 mm thick plaster over phuska
3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.263 ₹940.55 ₹247.36
Bhusa 0.263x35 = 9.20
5% wastage = 0.46
Total = 9.66 Kg. say 10 kg = 0.1 q
0308 Bhusa quintal 0.1 ₹530.00 ₹53.00
9999 Cowdung L.S. 5.33 ₹2.27 ₹12.10
9999 Mud mortar for gobri leaping L.S. 8.06 ₹2.27 ₹18.30
9977 Carriage of bhusa and cowdung L.S. 2.73 ₹2.27 ₹6.20
7904 Machine moulded common burnt clay tile bricks of class designation 12.5 1000 Nos 0.38 ₹5,200.00 ₹1,976.00
2207 Carriage of Brick tiles 1000 Nos 0.38 ₹0.00 ₹0.00
Cement mortar for grouting 1:3 (1 cement : 3 fine sand)
3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.061 ₹4,379.05 ₹267.12
Integral water proofing compound 2% by weight of cement
1213 Water proofing materials kilogram 0.006 ₹45.00 ₹0.27
9999 Sundries L.S. 6.76 ₹2.27 ₹15.35
LABOUR
0124 Mason 2nd class day 1.3 ₹816.00 ₹1,060.80
0114 Beldar day 3.75 ₹736.00 ₹2,760.00
0101 Bhisti day 1.1 ₹816.00 ₹897.60

Rate build-up

TOTAL ₹7,552.93
Add 1 % Water charges on "W" ₹75.53
TOTAL ₹7,628.46
Add GST on "X" (multiplying factor 0.2127) ₹1,622.57
TOTAL ₹9,251.03
Add 15% CPOH on "Y" ₹1,387.65
TOTAL ₹10,638.68
Add Cess @ 1% on "Z" ₹106.39
Cost of 10.00 sqm. ₹10,745.07
Cost of 1 Sqm. ₹1,074.51
Say ₹1,074.50