DSR 2023 · SH 11 · FLOORING

CPWD DSR item 11.44 rate analysis

Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge.

Published rate₹954.15per sqm
Rate analysis

Crazy ceramic tile flooring, with under layer 12 mm thick cement mortar 1:4 (1 cement: 4 coarse sand), with joints not exceeding 5 mm, including filling the gaps with ordinary cement mixture & mixing with synthetic polyester fibre, triangular in shape having specific gravity of 1.34 to 1.40, cross section size ranging from 10 to 40 micron & length upto 6 mm , mixing fibre @ 125 grams per 50 kg of cement in cement mortar, including providing and mixing water proofing material in mortar @ 1 kg per 50 kg of cement, all complete as per direction of Engineer-in-charge.

DSR rate₹954.15per sqm
Item code
11.44
Sub-head
SH 11 · FLOORING
Unit
sqm
Source row
3172

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm.
MATERIAL
Under layer 12 mm thick Cement mortar 1:4 (1 cement : 4 coarse sand).
3.9 Rate as per Item No.3.9 of SH:Mortar cum 0.14 ₹4,211.70 ₹589.64
LABOUR
0124 Mason 2nd class day 0.67 ₹816.00 ₹546.72
0114 Beldar day 0.75 ₹736.00 ₹552.00
0101 Bhisti day 0.92 ₹816.00 ₹750.72
9999 Sundries L.S. 8.97 ₹2.27 ₹20.36
Cement slurry for subgrade
0367 Portland Cement tonne 0.04 ₹5,156.00 ₹206.24
2209 Carriage of Cement tonne 0.04 ₹0.00 ₹0.00
Labour for applying cement slurry
0114 Beldar day 0.5 ₹736.00 ₹368.00
Top layer with tile piece and gap filling with cement motar:
Ceramic tile piece for crazy flooring
assuming 70% tile area and 30% of joint
filler/mixture. (7.00x0.010)=0.07
0.872x0.07/0.051=1.20 qtl
2709 Ceremic Tiles Pieces for Crazy Flooring quintal 1.2 ₹148.00 ₹177.60
9977 Carriage of tiles L.S. 62.4 ₹2.27 ₹141.65
Cement motar 1:4 for filling of crazy tile :(300x0.01=0.03)
3.9 Rate as per Item No.3.9 of SH:Mortar cum 0.03 ₹4,211.70 ₹126.35
Synthetic polyster triangular
4.18 Rate as per Item No.4.18 of SH: CONCRETE WORK per bag of 50kg of cement 1.38 ₹70.35 ₹97.08
Water proofing compound
4.12 Rate as per Item No.4.12 of SH:CONCRETE WORK per bag of 50kg of cement 1.38 ₹18.15 ₹25.05
0123 Mason 1st class day 1.2 ₹897.00 ₹1,076.40
0114 Beldar day 1 ₹736.00 ₹736.00
0115 Coolie day 1 ₹736.00 ₹736.00
0101 Bhisti day 0.54 ₹816.00 ₹440.64
9999 Sundries L.S. 67.25 ₹2.27 ₹152.66

Rate build-up

TOTAL ₹6,743.11
Add 1 % Water charges on "W-A" ₹66.21
TOTAL ₹6,809.32
Add GST on "X-A" (multiplying factor 0.2127) ₹1,422.37
TOTAL ₹8,231.69
Add 15% CPOH on "Y-A" ₹1,216.43
TOTAL ₹9,448.12
Add Cess @ 1% on "Z-A" ₹93.26
Cost of 10 sqm. ₹9,541.38
Cost of 1 sqm. ₹954.14
Say ₹954.15

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook