DSR 2023 · SH 11 · FLOORING

CPWD DSR item 11.34 rate analysis

38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete.

Published rate₹12,020.45DSR 2023
Rate analysis

38 mm thick wood block flooring of first class teak wood laid over 25 mm thick leveling layer of cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 10 mm nominal size) to be paid separately, coated with a thin layer of hot bitumen penetration 80/25 (blown type) @ 2.45 kg per sqm, including fixing blocks in position after dipping in hot bitumen (blown type) up to half depth, planed, levelled smooth and finished complete.

DSR rate₹12,020.45as per item analysis
Item code
11.34
Sub-head
SH 11 · FLOORING
Unit
See analysis
Source row
2351

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10sqm.
Bitumen blown type
i) For bed layer @ 2.45kg/sqm. = 2.45kg+
ii) For dipping blocks L.S. = 2.00Kg.
Total for 10sqm = 10X4.45kg = 44.5 kg
0313 Blown type petroleum bitumen of penetration 85/25 of approved quality tonne 0.044 ₹38,250.00 ₹1,683.00
2211 Carriage of Tar bitumen tonne 0.044 ₹0.00 ₹0.00
1st class teal wood in scanting for wooden blocks
10x1 sqm x 0.038 m = 0.38 cum
Add 10 % wastage = 0.038 cum
Total = 0.418 cum or 418 cudm
1187 First class teak wood in scantling 10 cudm 41.8 ₹880.00 ₹36,784.00
2204 Carriage of Timber cum 0.418 ₹0.00 ₹0.00
LABOUR
0111 Carpenter 1st class day 17.5 ₹897.00 ₹15,697.50
0114 Beldar day 22.5 ₹736.00 ₹16,560.00
0115 Coolie day 15 ₹736.00 ₹11,040.00
0130 Mistry day 1 ₹897.00 ₹897.00
9999 Sundries such as fuel, kerosene oil,
sand paper etc. L.S. 807.3 ₹2.27 ₹1,832.57

Rate build-up

TOTAL ₹84,494.07
Add 1 % Water charges on "W" ₹844.94
TOTAL ₹85,339.01
Add GST on "X" (multiplying factor 0.2127) ₹18,151.61
TOTAL ₹1,03,490.62
Add 15% CPOH on "Y" ₹15,523.59
TOTAL ₹1,19,014.21
Add Cess @ 1% on "Z" ₹1,190.14
Cost for 10 sqm. ₹1,20,204.35
Cost for 1 sqm. ₹12,020.44
Say ₹12,020.45