DSR 2023 · SH 11 · FLOORING

CPWD DSR item 11.26.1 rate analysis

Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) : 25 mm thick

Published rate₹1,948.25DSR 2023
Rate analysis

Kota stone slab flooring over 20 mm (average) thick base laid over and jointed with grey cement slurry mixed with pigment to match the shade of the slab, including rubbing and polishing complete with base of cement mortar 1 : 4 (1 cement : 4 coarse sand) :

DSR rate₹1,948.25as per item analysis

25 mm thick

Item code
11.26.1
Sub-head
SH 11 · FLOORING
Unit
See analysis
Source row
1978

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10sqm.
MATERIAL
1168 Kota stone slab 20 mm to 25 mm thick (semi-polished) including 15% wastage sqm 11.5 ₹320.00 ₹3,680.00
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.67 ₹0.00 ₹0.00
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 ₹4,211.70 ₹943.42
Cement for slurry-(i) for bedding = 44kg+
(ii) for joints = 20 kg.Total = 64 kg. or 0.064 tonne
0367 Portland Cement tonne 0.064 ₹5,156.00 ₹329.98
2209 Carriage of Cement tonne 0.064 ₹0.00 ₹0.00
0874 Black colour dark shade pigment kilogram 4.5 ₹75.00 ₹337.50
LABOUR
0124 Mason 2nd class day 1.2 ₹816.00 ₹979.20
0114 Beldar day 1 ₹736.00 ₹736.00
0115 Coolie day 1 ₹736.00 ₹736.00
0139 Skilled Beldar (for floor rubbing etc.) day 5 ₹816.00 ₹4,080.00
0013 Machine for rubbing of floors day 4 ₹350.00 ₹1,400.00
9999 Sundries L.S. 208.13 ₹2.27 ₹472.46

Rate build-up

TOTAL ₹13,694.56
Add 1 % Water charges on "W" ₹136.95
TOTAL ₹13,831.51
Add GST on "X" (multiplying factor 0.2127) ₹2,941.96
TOTAL ₹16,773.47
Add 15% CPOH on "Y" ₹2,516.02
TOTAL ₹19,289.49
Add Cess @ 1% on "Z" ₹192.89
Cost for 10sqm. ₹19,482.38
Cost for 1sqm. ₹1,948.24
Say ₹1,948.25