DSR 2023 · SH 10 · STEEL WORK

CPWD DSR item 10.5.1 rate analysis

Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer. Using M.S. angels 40x40x6 mm for diagonal braces

Published rate₹5,804.35per sqm
Rate analysis

Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6 mm angle iron and 3 mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer.

DSR rate₹5,804.35per sqm

Using M.S. angels 40x40x6 mm for diagonal braces

Item code
10.5.1
Sub-head
SH 10 · STEEL WORK
Unit
sqm
Source row
212

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 double leaf door of size 2.4mx2.4m=5.76sqm.
MATERIAL
(i) M.S. sheet 1mm thick
5.76sqm. @ 7.85kg/sqm. = 45.216kg.+
Add wastage @ 10% = 4.522kg.
Total = 49.738kg = 0.497 q
1013 Mild steel sheets for tanks quintal 0.497 ₹5,500.00 ₹2,733.50
(ii) Gusset plates 3.00mm thick
Area of one gusset plates
0.3x0.04 = 0.0120+
1/2x0.26(0.04+0.3) = 0.0442
Total = 0.0562sqm.+
8x0.0562 = 0.4496sqm.+
2x22/7x1/4x0.3x0.3=0.1414sqm.
Total = 0.5910sqm.
0.5910sqm.@23.55kg/sqm.=13.92kg.+
Add wastage @ 10% = 1.39kg
Total = 15.31kg. or 0.153q
1010 Mild steel plates quintal 0.153 ₹5,700.00 ₹872.10
(iii) Angle iron:40x40x6mm @3.5kg/m
Sides-4x2.40 = 9.6m+
Top & bottom-4x1.20=4.8m+
Diagonals-2x2.5=5.0m+
2x2.45 = 4.9m+
Total = 24.30m+
Add wastage @ 10% = 2.43m
Total =26.73m
26.73m @ 3.5kg. per m. = 93.56kg=0.936q
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.936 ₹5,965.00 ₹5,583.24
2205 Carriage of Steel tonne 0.159 ₹0.00 ₹0.00
(0.0497+0.0153+0.0936 tonne) = 0.1586 t say 0.159 tonne
1036 Iron pintels including welded pin each 4 ₹37.00 ₹148.00
1222 Mild steel sheets with bolts and nuts to rest on pintels each 4 ₹120.00 ₹480.00
1019 Mild steel hooks each 2 ₹32.00 ₹64.00
9999 Locking arrangements and handles L.S. 167.7 ₹2.27 ₹380.68
9999 Rivets L.S. 269.1 ₹2.27 ₹610.86
Priming coat-
M.S. sheet = 11.52
Angle iron-0.16x24.3 = 3.89
Total = 15.41
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 15.41 ₹67.40 ₹1,038.63
LABOUR
0116 Fitter (grade 1) day 2 ₹897.00 ₹1,794.00
0102 Blacksmith 1st class day 3 ₹897.00 ₹2,691.00
0103 Blacksmith 2nd class day 4 ₹816.00 ₹3,264.00
0123 Mason 1st class day 0.06 ₹897.00 ₹53.82
0124 Mason 2nd class day 0.06 ₹816.00 ₹48.96
0114 Beldar day 5 ₹736.00 ₹3,680.00
9999 Sundries L.S. 161.46 ₹2.27 ₹366.51

Rate build-up

TOTAL ₹23,809.30
Add 1 % Water charges on "W-A" ₹227.71
TOTAL ₹24,037.01
Add GST on "X-A" (multiplying factor 0.2127) ₹4,891.76
TOTAL ₹28,928.77
Add 15% CPOH on "Y-A" ₹4,183.52
TOTAL ₹33,112.29
Add Cess @ 1% on "Z-A" ₹320.74
Cost of 5.76 sqm. ₹33,433.03
Cost per sqm. ₹5,804.35
Say ₹5,804.35

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook