DSR 2023 · SH 10 · STEEL WORK

CPWD DSR item 10.3 rate analysis

Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer.

Published rate₹11,439.60per sqm
Rate analysis

Providing and fixing in position collapsible steel shutters with vertical channels 20x10x2 mm and braced with flat iron diagonals 20x5 mm size, with top and bottom rail of T-iron 40x40x6 mm, with 40 mm dia steel pulleys, complete with bolts, nuts, locking arrangement, stoppers, handles, including applying a priming coat of approved steel primer.

DSR rate₹11,439.60per sqm
Item code
10.3
Sub-head
SH 10 · STEEL WORK
Unit
sqm
Source row
78

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a gate 2.4mx1.5m = 3.6sqm.
MATERIAL
M.S. channels 18 Nos. on both sides
20x10x2mm @ 0.56kg/m
2x18x2.4 = 86.40m+
Add wastage @ 10% = 8.64m
Total = 95.04m
95.04m@0.56kg/m =53.22kg=0.53q
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.53 ₹5,965.00 ₹3,161.45
M.S. Tee-40x40x6mm
for bottom-1.570m+
for top = 1.725m
Total =3.295m Say 3.3m
3.3m @ 3.5kg/m = 11.55kg+
Add wastage @ 10% = 1.155 Kg.
Total = 12.705Kg. Say 0.13q
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.13 ₹5,965.00 ₹775.45
20mmx5mm flat iron diagonals 4 Nos.
4x32x0.5334 = 68.275m
68.275m @ 0.8kg/m = 54.62kg+
Add wastage @10% = 5.46kg
Total = 60.08kg = 0.60q
1008 Flats upto 10 mm in thickness quintal 0.6 ₹5,450.00 ₹3,270.00
2205 Carriage of Steel tonne 0.126 ₹0.00 ₹0.00
(0.053+0.013+0.060=0.126 tonne)
9999 Cost of rivets fixing hooks and washers L.S. 269.1 ₹2.27 ₹610.86
9999 Cost of locking arrangements and handles L.S. 67.34 ₹2.27 ₹152.86
4013 Pully 40 mm dia each 10 ₹40.00 ₹400.00
Priming coat-
Channel - 36x0.076x2.4 = 6.57sqm.+
Tee-0.16x3.3 = 0.53sqm.+
Flats-0.05x68 = 3.40sqm.
Total = 10.50sqm.
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 10.5 ₹67.40 ₹707.70
LABOUR
0116 Fitter (grade 1) day 3 ₹897.00 ₹2,691.00
0102 Blacksmith 1st class day 6 ₹897.00 ₹5,382.00
0103 Blacksmith 2nd class day 6 ₹816.00 ₹4,896.00
0123 Mason 1st class day 0.5 ₹897.00 ₹448.50
0124 Mason 2nd class day 0.5 ₹816.00 ₹408.00
0114 Beldar day 8 ₹736.00 ₹5,888.00
9999 Sundries L.S. 161.46 ₹2.27 ₹366.51

Rate build-up

TOTAL ₹29,158.33
Add 1 % Water charges on "W-A" ₹284.51
TOTAL ₹29,442.84
Add GST on "X-A" (multiplying factor 0.2127) ₹6,111.96
TOTAL ₹35,554.80
Add 15% CPOH on "Y-A" ₹5,227.07
TOTAL ₹40,781.87
Add Cess @ 1% on "Z-A" ₹400.74
Cost of 3.6sqm. ₹41,182.61
Cost per sqm. ₹11,439.61
Say ₹11,439.60