Rate analysis
Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approved steel primer.
DSR rate₹203.05per 1 kg
G.I. pipes
- Item code
- 10.26.3
- Sub-head
- SH 10 · STEEL WORK
- Unit
- 1 kg
- Source row
- 1352
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for hand rail of railing of two flights of staircase, length of hand rail = 5.40m i.e. 20.09 kg | |||||
| MATERIAL | |||||
| G.I. pipe 40mm nominal bore = 5.40m | |||||
| Add wastage @ 5% = 0.27m | |||||
| Total = 5.67m | |||||
| 1549 | G.I. pipes 40 mm dia | metre | 5.67 | ₹290.00 | ₹1,644.30 |
| 2271 | Carriage of G.I. pipes below 100 mm dia | tonne | 0.021 | ₹0.00 | ₹0.00 |
| (5.67m @ 3.72 kg/m = 21.09kg say 0.021 tonne | |||||
| Priming coat 40mm dia.Tube | |||||
| 5.4x22/7x0.0483 = 0.82 sqm | |||||
| 13.50.3 | Rate as per item no 13.50.3 of SH : Finishing | sqm | 0.82 | ₹67.40 | ₹55.27 |
| 1215 | Welding by electric plant | cm | 72 | ₹2.50 | ₹180.00 |
| (joints of hand rail and ballustards) | |||||
| 18x4x1.00 = 72cm | |||||
| LABOUR | |||||
| Labour for cutting assembling & erection | |||||
| 0102 | Blacksmith 1st class | day | 0.24 | ₹897.00 | ₹215.28 |
| 0114 | Beldar | day | 0.9 | ₹736.00 | ₹662.40 |
| 0100 | Bandhani | day | 0.12 | ₹816.00 | ₹97.92 |
| 9999 | Sundries | L.S. | 12.48 | ₹2.27 | ₹28.33 |
Rate build-up
| TOTAL | ₹2,883.50 |
| Add 1 % Water charges on "W-A" | ₹28.28 |
| TOTAL | ₹2,911.78 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹607.58 |
| TOTAL | ₹3,519.36 |
| Add 15% CPOH on "Y-A" | ₹519.61 |
| TOTAL | ₹4,038.97 |
| Add Cess @ 1% on "Z-A" | ₹39.84 |
| Cost of 20.09 Kg. | ₹4,078.81 |
| Cost per 1 kg. | ₹203.03 |
| Say | ₹203.05 |