Rate analysis
Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete.
DSR rate₹226.00as per item analysis
- Item code
- 10.17
- Sub-head
- SH 10 · STEEL WORK
- Unit
- See analysis
- Source row
- 1121
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 clamp | |||||
| MATERIAL | |||||
| 16mm dia. M.S. bar 1m @ 1.58 kg/m | |||||
| 1x1.58 = 1.58Kg+ | |||||
| Add wastage @ 5% = 0.08 Kg. | |||||
| Total = 1.66 Kg. | |||||
| 1003 | Mild steel round bar above 12 mm dia | quintal | 0.017 | ₹5,450.00 | ₹92.65 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.04 | ₹816.00 | ₹32.64 |
| 0114 | Beldar | day | 0.04 | ₹736.00 | ₹29.44 |
| 9988 | Sundries (Carriage, fixing and painting etc.) | L.S. | 1.82 | ₹2.27 | ₹4.13 |
Rate build-up
| Say 1.70kg. or 0.017q | — |
| TOTAL | ₹158.86 |
| Add 1 % Water charges on "W" | ₹1.59 |
| TOTAL | ₹160.45 |
| Add GST on "X" (multiplying factor 0.2127) | ₹34.13 |
| TOTAL | ₹194.58 |
| Add 15% CPOH on "Y" | ₹29.19 |
| TOTAL | ₹223.77 |
| Add Cess @ 1% on "Z" | ₹2.24 |
| Cost for 1 clamp | ₹226.01 |
| Say | ₹226.00 |