Rate analysis
Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-sections, joints mitred and welded, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer.
DSR rate₹141.70as per item analysis
Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size).
- Item code
- 10.13.1
- Sub-head
- SH 10 · STEEL WORK
- Unit
- See analysis
- Source row
- 620
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 17.5Kg. | |||||
| MATERIAL | |||||
| Tee iron 40x40x6mm = 2m+2m+1m = 5 metres | |||||
| 5 metres @3.5Kg/m = 17.5kg.+ | |||||
| Add wastage @ 5% = 0.87Kg. | |||||
| Total = 18.37 kg. Say 0.18 qunital | |||||
| 1007 | Structurals such as tees,angles channels and R.S. joists | quintal | 0.18 | ₹5,965.00 | ₹1,073.70 |
| M.S. bars 10mm = 1x1m = 1 metre | |||||
| 1 metre @ 0.60kg/m = 0.60Kg.+ | |||||
| Add wastage @ 5% = 0.03Kg. | |||||
| Total = 0.63 Kg. Say = 0.006 qunital | |||||
| 1002 | Mild steel round bar 12 mm dia and below | quintal | 0.006 | ₹5,550.00 | ₹33.30 |
| M.S. flat 15x3mm = 6x10cm = 0.60 metre | |||||
| 0.6 metre @ 0.35kg/m = 0.21Kg+ | |||||
| Add wastage @ 5% = 0.01 Kg. | |||||
| Total = 0.22 kg = 0.002q. | |||||
| 1008 | Flats upto 10 mm in thickness | quintal | 0.002 | ₹5,450.00 | ₹10.90 |
| Cement concrete block 1:3:6- 6x15x10x10cm= 0.009 cum | |||||
| 4.2.5 | Rate as per item no 4.2.5 of SH : Concrete work | cum | 0.009 | ₹9,311.40 | ₹83.80 |
| 0595 | Bright finished or black enamelled mild steel butt hinges 100x58x1.90 mm | 10 Nos | 0.6 | ₹80.00 | ₹48.00 |
| 9999 | For screws and nuts and bolts | L.S. | 35.88 | ₹2.27 | ₹81.45 |
| 9999 | For applying steel primer | L.S. | 17.94 | ₹2.27 | ₹40.72 |
| 9977 | Carriage of material | L.S. | 5.33 | ₹2.27 | ₹12.10 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.1 | ₹816.00 | ₹81.60 |
| 0116 | Fitter (grade 1) | day | 0.15 | ₹897.00 | ₹134.55 |
| 0114 | Beldar | day | 0.2 | ₹736.00 | ₹147.20 |
| 9999 | Sundries | L.S. | 8.97 | ₹2.27 | ₹20.36 |
Rate build-up
| TOTAL | ₹1,767.68 |
| Add 1 % Water charges on "W-A" | ₹16.84 |
| TOTAL | ₹1,784.52 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹361.74 |
| TOTAL | ₹2,146.26 |
| Add 15% CPOH on "Y-A" | ₹309.37 |
| TOTAL | ₹2,455.63 |
| Add Cess @ 1% on "Z-A" | ₹23.72 |
| Cost for 17.5Kg. | ₹2,479.35 |
| Cost for 1 Kg. | ₹141.68 |
| Say | ₹141.70 |