DSR 2023 · SH 10 · STEEL WORK

CPWD DSR item 10.13.1 rate analysis

Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-sections, joints mitred and welded, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer. Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size).

Published rate₹141.70DSR 2023
Rate analysis

Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-sections, joints mitred and welded, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer.

DSR rate₹141.70as per item analysis

Fixing with 15x3 mm lugs 10 cm long embedded in cement concrete block 15x10x10 cm of C.C. 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size).

Item code
10.13.1
Sub-head
SH 10 · STEEL WORK
Unit
See analysis
Source row
620

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 17.5Kg.
MATERIAL
Tee iron 40x40x6mm = 2m+2m+1m = 5 metres
5 metres @3.5Kg/m = 17.5kg.+
Add wastage @ 5% = 0.87Kg.
Total = 18.37 kg. Say 0.18 qunital
1007 Structurals such as tees,angles channels and R.S. joists quintal 0.18 ₹5,965.00 ₹1,073.70
M.S. bars 10mm = 1x1m = 1 metre
1 metre @ 0.60kg/m = 0.60Kg.+
Add wastage @ 5% = 0.03Kg.
Total = 0.63 Kg. Say = 0.006 qunital
1002 Mild steel round bar 12 mm dia and below quintal 0.006 ₹5,550.00 ₹33.30
M.S. flat 15x3mm = 6x10cm = 0.60 metre
0.6 metre @ 0.35kg/m = 0.21Kg+
Add wastage @ 5% = 0.01 Kg.
Total = 0.22 kg = 0.002q.
1008 Flats upto 10 mm in thickness quintal 0.002 ₹5,450.00 ₹10.90
Cement concrete block 1:3:6- 6x15x10x10cm= 0.009 cum
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.009 ₹9,311.40 ₹83.80
0595 Bright finished or black enamelled mild steel butt hinges 100x58x1.90 mm 10 Nos 0.6 ₹80.00 ₹48.00
9999 For screws and nuts and bolts L.S. 35.88 ₹2.27 ₹81.45
9999 For applying steel primer L.S. 17.94 ₹2.27 ₹40.72
9977 Carriage of material L.S. 5.33 ₹2.27 ₹12.10
LABOUR
0103 Blacksmith 2nd class day 0.1 ₹816.00 ₹81.60
0116 Fitter (grade 1) day 0.15 ₹897.00 ₹134.55
0114 Beldar day 0.2 ₹736.00 ₹147.20
9999 Sundries L.S. 8.97 ₹2.27 ₹20.36

Rate build-up

TOTAL ₹1,767.68
Add 1 % Water charges on "W-A" ₹16.84
TOTAL ₹1,784.52
Add GST on "X-A" (multiplying factor 0.2127) ₹361.74
TOTAL ₹2,146.26
Add 15% CPOH on "Y-A" ₹309.37
TOTAL ₹2,455.63
Add Cess @ 1% on "Z-A" ₹23.72
Cost for 17.5Kg. ₹2,479.35
Cost for 1 Kg. ₹141.68
Say ₹141.70

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook