Providing and fixing factory made ISI marked steel glazed doors, windows and ventilators, side /top /centre hung, with beading and all members such as F7D,F4B, K11 B and K12 B etc. complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted, including providing and fixing of hinges, pivots, priming coat of approved steel primer, but excluding the cost of other fittings,glass panes complete all as per approved design, (sectional weight of only steel members shall be measured for payment).
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid for separately)
Published rate₹128.25per kg
Rate analysis
Providing and fixing factory made ISI marked steel glazed doors, windows and ventilators, side /top /centre hung, with beading and all members such as F7D,F4B, K11 B and K12 B etc. complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted, including providing and fixing of hinges, pivots, priming coat of approved steel primer, but excluding the cost of other fittings,glass panes complete all as per approved design, (sectional weight of only steel members shall be measured for payment).
DSR rate₹128.25per kg
Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid for separately)
Item code
10.11.2
Sub-head
SH 10 · STEEL WORK
Unit
kg
Source row
536
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 10 Nos. double leaf door of size 2.075x1.175m = 2.44 sqm. (weight 30 kg).
Weight for 10 Nos. door = 10x30 = 300 kg
MATERIAL
1011
Steel glazed door,window/ ventilator, all members like as F7D, F4B, K11 and K12B etc.
kg
300
₹59.00
₹17,700.00
9977
Carriage of Steel Door
L.S.
403.7
₹2.27
₹916.40
Labour for fabrication
0103
Blacksmith 2nd class
day
1.7
₹816.00
₹1,387.20
0116
Fitter (grade 1)
day
2.6
₹897.00
₹2,332.20
0114
Beldar
day
3.4
₹736.00
₹2,502.40
9999
Sundries
L.S.
153.7
₹2.27
₹348.90
Labour for fixing
0114
Beldar
day
0.27
₹736.00
₹198.72
0115
Collie
day
0.195
₹736.00
₹143.52
0130
Mistry
day
0.084
₹897.00
₹75.35
0128
Mate
day
0.012
₹816.00
₹9.79
9999
Hire charges of drill machine, scaffolding and sundries
L.S.
122.2
₹2.27
₹277.39
Apply steel primer (2.44x1.00 for both sides)= 10x2.44 sqm = 24.4 sqm
13.50.3
Rate as per item no 13.50.3 of SH : Finishing
sqm
24.4
₹67.40
₹1,644.56
Rate build-up
TOTAL
₹27,536.43
Add 1 % Water charges on "W-A"
₹258.92
TOTAL
₹27,795.35
Add GST on "X-A" (multiplying factor 0.2127)
₹5,562.27
TOTAL
₹33,357.62
Add 15% CPOH on "Y-A"
₹4,756.96
TOTAL
₹38,114.58
Add Cess @ 1% on "Z-A"
₹364.70
Cost for 300 kg.
₹38,479.28
Cost of 1 kg.
₹128.26
Say
₹128.25