DSR 2023 · SH 10 · STEEL WORK

CPWD DSR item 10.11.2 rate analysis

Providing and fixing factory made ISI marked steel glazed doors, windows and ventilators, side /top /centre hung, with beading and all members such as F7D,F4B, K11 B and K12 B etc. complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted, including providing and fixing of hinges, pivots, priming coat of approved steel primer, but excluding the cost of other fittings,glass panes complete all as per approved design, (sectional weight of only steel members shall be measured for payment). Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid for separately)

Published rate₹128.25per kg
Rate analysis

Providing and fixing factory made ISI marked steel glazed doors, windows and ventilators, side /top /centre hung, with beading and all members such as F7D,F4B, K11 B and K12 B etc. complete of standard rolled steel sections, joints mitred and flash butt welded and sash bars tenoned and riveted, including providing and fixing of hinges, pivots, priming coat of approved steel primer, but excluding the cost of other fittings,glass panes complete all as per approved design, (sectional weight of only steel members shall be measured for payment).

DSR rate₹128.25per kg

Fixing with carbon steel galvanised dash fastener of required dia and size (to be paid for separately)

Item code
10.11.2
Sub-head
SH 10 · STEEL WORK
Unit
kg
Source row
536

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Nos. double leaf door of size 2.075x1.175m = 2.44 sqm. (weight 30 kg). Weight for 10 Nos. door = 10x30 = 300 kg
MATERIAL
1011 Steel glazed door,window/ ventilator, all members like as F7D, F4B, K11 and K12B etc. kg 300 ₹59.00 ₹17,700.00
9977 Carriage of Steel Door L.S. 403.7 ₹2.27 ₹916.40
Labour for fabrication
0103 Blacksmith 2nd class day 1.7 ₹816.00 ₹1,387.20
0116 Fitter (grade 1) day 2.6 ₹897.00 ₹2,332.20
0114 Beldar day 3.4 ₹736.00 ₹2,502.40
9999 Sundries L.S. 153.7 ₹2.27 ₹348.90
Labour for fixing
0114 Beldar day 0.27 ₹736.00 ₹198.72
0115 Collie day 0.195 ₹736.00 ₹143.52
0130 Mistry day 0.084 ₹897.00 ₹75.35
0128 Mate day 0.012 ₹816.00 ₹9.79
9999 Hire charges of drill machine, scaffolding and sundries L.S. 122.2 ₹2.27 ₹277.39
Apply steel primer (2.44x1.00 for both sides)= 10x2.44 sqm = 24.4 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 24.4 ₹67.40 ₹1,644.56

Rate build-up

TOTAL ₹27,536.43
Add 1 % Water charges on "W-A" ₹258.92
TOTAL ₹27,795.35
Add GST on "X-A" (multiplying factor 0.2127) ₹5,562.27
TOTAL ₹33,357.62
Add 15% CPOH on "Y-A" ₹4,756.96
TOTAL ₹38,114.58
Add Cess @ 1% on "Z-A" ₹364.70
Cost for 300 kg. ₹38,479.28
Cost of 1 kg. ₹128.26
Say ₹128.25

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook