Rate analysis
Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.
DSR rate₹117.35per Kg
- Item code
- 10.1
- Sub-head
- SH 10 · STEEL WORK
- Unit
- Kg
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for one qunital | |||||
| MATERIAL | |||||
| Steel = 1.00q | |||||
| Add wastage @ 5% = 0.05q | |||||
| Total = 1.05q | |||||
| 1007 | Structurals such as tees,angles channels and R.S. joists | quintal | 1.05 | ₹5,965.00 | ₹6,263.25 |
| 2205 | Carriage of Steel | tonne | 0.105 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0116 | Fitter (grade 1) | day | 0.5 | ₹897.00 | ₹448.50 |
| 0103 | Blacksmith 2nd class | day | 0.75 | ₹816.00 | ₹612.00 |
| 0114 | Beldar | day | 1 | ₹736.00 | ₹736.00 |
| Priming Coat | |||||
| 13.50.3 | Rate as per Item Number 13.50.3 of | — | — | — | — |
| — | SH:Finishing | sqm | 3 | ₹67.40 | ₹202.20 |
| 9999 | Sundries | L.S. | 20.67 | ₹2.27 | ₹46.92 |
Rate build-up
| TOTAL | ₹8,308.87 |
| Add 1 % Water charges on "W-A" | ₹81.07 |
| TOTAL | ₹8,389.94 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹1,741.53 |
| TOTAL | ₹10,131.47 |
| Add 15% CPOH on "Y-A" | ₹1,489.39 |
| TOTAL | ₹11,620.86 |
| Add Cess @ 1% on "Z-A" | ₹114.19 |
| Cost of 1qunital | ₹11,735.05 |
| Cost of 1 Kg. | ₹117.35 |
| Say | ₹117.35 |