DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.9.3.1 rate analysis

Providing and fixing glazed shutters for doors, windows and clerestory windows using 4 mm thick float glass panes (weight not less than 10 kg per sqm) fixing with ISI marked M.S. pressed butt hinges bright finished of required size with necessary screws. Kiln seasoned selected planks of sheesham wood 35 mm thick

Published rate₹4,401.55per sqm
Rate analysis

Providing and fixing glazed shutters for doors, windows and clerestory windows using 4 mm thick float glass panes (weight not less than 10 kg per sqm) fixing with ISI marked M.S. pressed butt hinges bright finished of required size with necessary screws. Kiln seasoned selected planks of sheesham wood

DSR rate₹4,401.55per sqm

35 mm thick

Item code
9.9.3.1
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
866

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for shutters of a door (glazed)
200x108cm = 2.16 sqm.
MATERIAL
Sheesham wood
Styles :
4x200x9.5x3.5cm = 0.027cum+
Rails
Top & intermediate rails
2x110.5x9.5x3.5cm = 0.008cum+
Lock and bottom rails
2x110.5x19.7x3.5cm = 0.015cum.+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.053 cum.+
Add for wastage @ 10% = 0.005cum.
Grand Total = 0.058 cum or = 58 cudm
1200 Kiln seasoned selected sheesum wood planks 10 cudm 5.8 ₹650.00 ₹3,770.00
2406 Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm). sqm 1.27 ₹321.00 ₹407.67
0595 Bright finished or black enamelled mild steel butt hinges 100x58x1.90 mm 10 Nos 0.6 ₹80.00 ₹48.00
0597 Bright finished or black enamelled mild steel butt hinges50x37x1.50 mm 10 Nos 0.2 ₹49.00 ₹9.80
0637 Bright finished or black enamelled mild steel screws 40 mm 100 Nos 0.48 ₹62.00 ₹29.76
0640 Bright finished or black enamelled mild steel screws 20 mm 100 Nos 0.08 ₹40.00 ₹3.20
2204 Carriage of Timber cum 0.058 ₹0.00 ₹0.00
LABOUR
0156 Carpenter (average) day 1.83 ₹857.00 ₹1,568.31
0119 Glazier day 0.23 ₹816.00 ₹187.68
0114 Beldar day 0.77 ₹736.00 ₹566.72
9999 Sundries L.S. 40.43 ₹2.27 ₹91.78

Rate build-up

TOTAL ₹6,682.92
Add 1 % Water charges on "W" ₹66.83
TOTAL ₹6,749.75
Add GST on "X" (multiplying factor 0.2127) ₹1,435.67
TOTAL ₹8,185.42
Add 15% CPOH on "Y" ₹1,227.81
TOTAL ₹9,413.23
Add Cess @ 1% on "Z" ₹94.13
Cost of 2.16 sqm. ₹9,507.36
Cost of 1 sqm. ₹4,401.56
Say ₹4,401.55

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook