DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.27.1.2.2 rate analysis

Providing and fixing wire gauge shutters using galvanized M.S. wire gauge of average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm, for doors, windows and clerestory windows with hinges and necessary screws : 35 mm thick shutters With ISI marked stainless steel butt hinges of required size Kiln seasoned and chemically treated hollock wood

Published rate₹3,792.95per sqm
Rate analysis

Providing and fixing wire gauge shutters using galvanized M.S. wire gauge of average width of aperture 1.4 mm in both directions with wire of dia 0.63 mm, for doors, windows and clerestory windows with hinges and necessary screws : 35 mm thick shutters With ISI marked stainless steel butt hinges of required size

DSR rate₹3,792.95per sqm

Kiln seasoned and chemically treated hollock wood

Item code
9.27.1.2.2
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
1793

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for door shutters 2.00x1.08m = 2.16 sqm.
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+
Beadings - (2x312+2x150)x(1.2)x(1.2)cm = 0.001 cum.
Total = 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
2505 Hollock wood in planks 10 cudm 5.14 ₹409.00 ₹2,102.26
2504 Kiln seasoning of timber cum 0.0514 ₹794.00 ₹40.81
9999 Chemical treatment L.S. 8.97 ₹2.27 ₹20.36
Wire gauge 2x160x40cm = 1.28 sqm.+ Add wastage @ 10% = 0.13 sqm. Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture 1.4 mm and nominal dia. Of wire 0.63 mm sqm 1.41 ₹260.00 ₹366.60
8220 Stainless steel butt hinges (heavy weight) 100x60x2.5 mm IS : 12817 marked 10 Nos 0.6 ₹345.00 ₹207.00
8218 Stainless steel butt hinges 50x37x1.5 mm IS : 12817 marked 10 Nos 0.2 ₹170.00 ₹34.00
8211 Stainless steel screws 40 mm 100 Nos 0.48 ₹270.00 ₹129.60
8214 Stainless steel screws 20 mm 100 Nos 0.08 ₹175.00 ₹14.00
2204 Carriage of Timber cum 0.0514 ₹0.00 ₹0.00
LABOUR
0111 Carpenter 1st class day 1.3 ₹897.00 ₹1,166.10
0112 Carpenter 2nd class day 0.9 ₹816.00 ₹734.40
0114 Beldar day 1.05 ₹736.00 ₹772.80
0130 Mistry day 0.105 ₹897.00 ₹94.19
9999 Sundries L.S. 33.8 ₹2.27 ₹76.73

Rate build-up

Say 51.4 cudm.
TOTAL ₹5,758.85
Add 1 % Water charges on "W" ₹57.59
TOTAL ₹5,816.44
Add GST on "X" (multiplying factor 0.2127) ₹1,237.16
TOTAL ₹7,053.60
Add 15% CPOH on "Y" ₹1,058.04
TOTAL ₹8,111.64
Add Cess @ 1% on "Z" ₹81.12
Cost of 2.16 sqm. ₹8,192.76
Cost of 1 sqm. ₹3,792.94
Say ₹3,792.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook