DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.23 rate analysis

Extra for providing lipping with 2nd class teak wood battens 25 mm minimum depth on all edges of flush door shutters (over all area of door shutter to be measured).

Published rate₹462.35DSR 2023
Rate analysis

Extra for providing lipping with 2nd class teak wood battens 25 mm minimum depth on all edges of flush door shutters (over all area of door shutter to be measured).

DSR rate₹462.35as per item analysis
Item code
9.23
Sub-head
SH 9 · WOOD & PVC WORK
Unit
See analysis
Source row
1716

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 sqm. of door area
0752 Block board construction flush door lipping sqm of door area 1 ₹325.00 ₹325.00

Rate build-up

TOTAL ₹325.00
Add 1 % Water charges on "W" ₹3.25
TOTAL ₹328.25
Add GST on "X" (multiplying factor 0.2127) ₹69.82
TOTAL ₹398.07
Add 15% CPOH on "Y" ₹59.71
TOTAL ₹457.78
Add Cess @ 1% on "Z" ₹4.58
Cost for 1 sqm ₹462.36
Say ₹462.35