DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.16.1.2 rate analysis

Providing and fixing 25 mm thick shutters for cup board etc. : Panelled or panelled & glazed shutters : Second class teak wood including ISI marked nickel plated bright finished M.S. piano hinges with necessary screws

Published rate₹4,542.90per sqm
Rate analysis

Providing and fixing 25 mm thick shutters for cup board etc. : Panelled or panelled & glazed shutters :

DSR rate₹4,542.90per sqm

Second class teak wood including ISI marked nickel plated bright finished M.S. piano hinges with necessary screws

Item code
9.16.1.2
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
1276

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for shutters of a cup-board (half glazed and half panelled) 200x108cm = 2.16 sqm.
MATERIAL
Styles-
4x200x8.0x2.5cm = 0.016 cum+
Rails-
Top rail-
1x110.5x8.0x2.5cm = 0.0022cum+
Lock and bottom rail-
2x110.5x8.0x2.5cm = 0.0044 cum.
Panels-
2x48x41x1.6cm = 0.006cum+
Sash bars-
2x114x3.8x2.5cm = 0.003cum+
6x48x3.8x2.5cm = 0.003 cum+
Beading-
16x92x1.4x1.2cm = 0.002cum
Total = 0.0366
Add for wastage @ 10% = 0.0037 cum.
Grand Total = 0.0403 cum or 40 cudm
1190 Second class teak wood in planks 10 cudm 4 ₹791.00 ₹3,164.00
2204 Carriage of Timber cum 0.04 ₹0.00 ₹0.00
2406 Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm). sqm 0.99 ₹321.00 ₹317.79
Fittings-
0608 Nickel plated mild steel piono hinges 1 mm thick 25 mm wide metre 4 ₹42.00 ₹168.00
0586 Chromium plated Brass screws 40 mm 100 Nos 1.14 ₹254.00 ₹289.56
LABOUR
0111 Carpenter 1st class day 2.4 ₹897.00 ₹2,152.80
0119 Glazier day 0.18 ₹816.00 ₹146.88
0114 Beldar day 0.77 ₹736.00 ₹566.72
9999 Sundries L.S. 40.43 ₹2.27 ₹91.78

Rate build-up

TOTAL ₹6,897.53
Add 1 % Water charges on "W" ₹68.98
TOTAL ₹6,966.51
Add GST on "X" (multiplying factor 0.2127) ₹1,481.78
TOTAL ₹8,448.29
Add 15% CPOH on "Y" ₹1,267.24
TOTAL ₹9,715.53
Add Cess @ 1% on "Z" ₹97.16
Cost of 2.16 sqm. ₹9,812.69
Cost of 1 sqm. ₹4,542.91
Say ₹4,542.90