Providing and fixing 37 mm thick factory made PVC door shutter, styles and rails made of PVC hollow section of size 100 mm x 37 mm with wall thickness 2 mm (± 0.2 mm), with inbuilt bead on one side, styles and rails mitered cut and joint at the corners by means of 2 nos of plastic brackets of size 75 mm x 220 mm at each corner and stainless steel screws, reinforcing the hinge side of style by inserting PVC profile of size 28 mm x 30 mm, with wall thickness 2 mm ( ± 0.2 mm). Lockrail of size 100 mm x 37 mm, wall thickness 2 mm (+ 0.2 mm) will be fixed to the vertical styles. Providing with PVC snapfit beads and panel of size 100 mm x 20 mm, and inserting 2 nos tie bar of 6 mm dia and fastening with nuts and washers complete, all as per manufacturer's specification and direction of Engineer-in-charge.
Published rate₹4,076.05per sqm
Rate analysis
Providing and fixing 37 mm thick factory made PVC door shutter, styles and rails made of PVC hollow section of size 100 mm x 37 mm with wall thickness 2 mm (± 0.2 mm), with inbuilt bead on one side, styles and rails mitered cut and joint at the corners by means of 2 nos of plastic brackets of size 75 mm x 220 mm at each corner and stainless steel screws, reinforcing the hinge side of style by inserting PVC profile of size 28 mm x 30 mm, with wall thickness 2 mm ( ± 0.2 mm). Lockrail of size 100 mm x 37 mm, wall thickness 2 mm (+ 0.2 mm) will be fixed to the vertical styles. Providing with PVC snapfit beads and panel of size 100 mm x 20 mm, and inserting 2 nos tie bar of 6 mm dia and fastening with nuts and washers complete, all as per manufacturer's specification and direction of Engineer-in-charge.
DSR rate₹4,076.05per sqm
Item code
9.144
Sub-head
SH 9 · WOOD & PVC WORK
Unit
sqm
Source row
7896
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for of one shutter 2.20x1.08m = 2.38 sqm
MATERIAL
8746
37 mm thick Factory made shutter with style,rails and panels of PVC extruded section in white or grey finish i/c carriage
sqm
2.38
₹2,578.00
₹6,135.64
LABOUR
0156
Carpenter (average)
day
0.4
₹857.00
₹342.80
0114
Beldar
day
0.4
₹736.00
₹294.40
9999
Sundries
L.S.
20.36
₹2.27
₹46.22
Rate build-up
TOTAL
₹6,819.06
Add 1 % Water charges on "W"
₹68.19
TOTAL
₹6,887.25
Add GST on "X" (multiplying factor 0.2127)
₹1,464.92
TOTAL
₹8,352.17
Add 15% CPOH on "Y"
₹1,252.83
TOTAL
₹9,605.00
Add Cess @ 1% on "Z"
₹96.05
Cost of 2.38 sqm
₹9,701.05
Cost of 1 sqm
₹4,076.07
Say
₹4,076.05
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.