DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.7.2 rate analysis

Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately). Stainless steel cramps

Published rate₹714.40per kg
Rate analysis

Providing and fixing cramps of required size & shape in RCC/ CC / Brick masonry backing with cement mortar 1:2 ( 1 cement :2 coarse sand), including drilling necessary hole in stones and embedding the cramp in the hole (fastener to be paid separately).

DSR rate₹714.40per kg

Stainless steel cramps

Item code
8.7.2
Sub-head
SH 8 · CLADDING WORK
Unit
kg
Source row
330

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 0.934 kg
MATERIAL
Stainless steel cramp
10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^(-5)
10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^(-5)
= 13.3 x 10^(-5)
less hole 10 x 0.024 x 0.010 x 0.006 = 1.4 x 10^(-5)
= 11.9 x 10^5 x 7850 = 0.934 kg
Add wastage @ 5% = 0.047kg.
Total = 0.981 kg.
7339 Stainless steel cramp kilogram 0.981 ₹313.00 ₹307.05
9977 Carriage L.S. 3.9 ₹2.27 ₹8.85
Cement mortar 1:2 (1 cement : 2 coarse sand)
3.7 Rate as per Item Number 3.7 of SH: Mortars cum 0.001 ₹5,584.50 ₹5.58
9999 Labour for fixing in position L.S. 65 ₹2.27 ₹147.55

Rate build-up

TOTAL ₹469.03
Add 1 % Water charges on "W" ₹4.69
TOTAL ₹473.72
Add GST on "X" (multiplying factor 0.2127) ₹100.76
TOTAL ₹574.48
Add 15% CPOH on "Y" ₹86.17
TOTAL ₹660.65
Add Cess @ 1% on "Z" ₹6.61
Cost for 0.934 kg. ₹667.26
Cost per kg ₹714.41
Say ₹714.40