DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.29 rate analysis

Providing and fixing 4mm thick coir veneer board, ISI marked IS : 14842, plain lining with necessary screws, priming coat on unexposed surface etc., complete.

Published rate₹1,825.05per sqm
Rate analysis

Providing and fixing 4mm thick coir veneer board, ISI marked IS : 14842, plain lining with necessary screws, priming coat on unexposed surface etc., complete.

DSR rate₹1,825.05per sqm
Item code
8.29
Sub-head
SH 8 · CLADDING WORK
Unit
sqm
Source row
2077

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10sqm.
MATERIAL
Coir veneered board 4mm thick = 10sqm.
Add for wastage @ 20% = 2 sqm.
Total = 12 sqm.
7552 Coir veneered board 4mm thick sqm 12 ₹274.00 ₹3,288.00
9977 Carriage of Coir veneered board L.S. 5.46 ₹2.27 ₹12.39
Second class teak wood plugs including cutting brick work and fixing in cement mortar 1:3 (1 cement: 3 fine sand)
8.23 Rate as per item no 8.23 of SH : Cladding Work each 55 ₹40.85 ₹2,246.75
LABOUR
0111 Carpenter 1st class day 3.8 ₹897.00 ₹3,408.60
0114 Beldar day 4.6 ₹736.00 ₹3,385.60
0130 Mistry day 0.6 ₹897.00 ₹538.20
9999 20mm nails without head for fixing ply L.S. 53.82 ₹2.27 ₹122.17
Priming coat Painting with ready mixed priming coat
13.85.1 Rate as per item no 13.85.1 of SH : Finishing sqm 10 ₹70.35 ₹703.50

Rate build-up

TOTAL ₹13,705.21
Add 1 % Water charges on "W-A" ₹107.55
TOTAL ₹13,812.76
Add GST on "X-A" (multiplying factor 0.2127) ₹2,310.46
TOTAL ₹16,123.22
Add 15% CPOH on "Y-A" ₹1,975.95
TOTAL ₹18,099.17
Add Cess @ 1% on "Z-A" ₹151.49
Cost of 10 sqm. ₹18,250.66
Cost of 1 sqm. ₹1,825.07
Say ₹1,825.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.