DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.27.1 rate analysis

Providing and fixing specified wood frame work consisting of battens 50x25mm fixed with rawl plug and drilling necessary holes for rawl plug etc. including priming coat complete. Kiln seasoned and chemically treated hollock wood

Published rate₹1,87,277.65per cum
Rate analysis

Providing and fixing specified wood frame work consisting of battens 50x25mm fixed with rawl plug and drilling necessary holes for rawl plug etc. including priming coat complete.

DSR rate₹1,87,277.65per cum

Kiln seasoned and chemically treated hollock wood

Item code
8.27.1
Sub-head
SH 8 · CLADDING WORK
Unit
cum
Source row
2016

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 500 no. battens of size 500cmx50mmx25mm = 3125 cudm=3.125 cum
MATERIAL
Hollock wood- 500x5.00x0.50x0.025 = 3125 cum
Add wastage @ 5% = 0.156 cum.
Total = 3.281 cum Say 3300 cudm.
2505 Hollock wood in planks 10 cudm 330 ₹409.00 ₹1,34,970.00
2204 Carriage of Timber cum 3.3 ₹0.00 ₹0.00
LABOUR
0111 Carpenter 1st class day 100 ₹897.00 ₹89,700.00
0114 Beldar day 25 ₹736.00 ₹18,400.00
9999 Sundries L.S. 676 ₹2.27 ₹1,534.52
Painting with ready mixed priming coat on ground 500x5.00x0.15 m =375 sqm
13.85.1 Rate as per item no 13.85.1 of SH : Finishing sqm 375 ₹70.35 ₹26,381.25
7048 Rawl plug 50 mm (designation 10 no.) each 5,500 ₹24.00 ₹1,32,000.00
9999 Labour for drilling holes, steel tape, sundries etc. L.S. 7,150 ₹2.27 ₹16,230.50

Rate build-up

TOTAL ₹4,19,216.27
Add 1 % Water charges on "W-A" ₹3,928.35
TOTAL ₹4,23,144.62
Add GST on "X-A" (multiplying factor 0.2127) ₹84,391.57
TOTAL ₹5,07,536.19
Add 15% CPOH on "Y-A" ₹72,173.24
TOTAL ₹5,79,709.43
Add Cess @ 1% on "Z-A" ₹5,533.28
Cost of 3.125 cum ₹5,85,242.71
Cost of 1 cum. ₹1,87,277.67
Say ₹1,87,277.65

Use this rate in the interactive workbook