DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.25.4 rate analysis

Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface. 12 mm thick

Published rate₹2,423.25per sqm
Rate analysis

Providing and fixing 2nd class teak wood plain lining tongued and grooved, including wooden plugs complete with necessary screws and priming coat on unexposed surface.

DSR rate₹2,423.25per sqm

12 mm thick

Item code
8.25.4
Sub-head
SH 8 · CLADDING WORK
Unit
sqm
Source row
1807

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost of 10 sqm
Wood-
Second class teak wood 10x0.012 = 0.12 cum+
Add wastage @ 10% = 0.012 cum.
Total = 0.132 cum. Say 132 cudm.
1190 Second class teak wood in planks 10 cudm 13.2 ₹791.00 ₹10,441.20
1231 Extra for selected planks of second class teakwood 10 cudm 13.2 ₹150.00 ₹1,980.00
2204 Carriage of Timber cum 0.132 ₹0.00 ₹0.00
Second class teak wood plugs including cutting brick work and fixing in cement mortar 1:3 (1 cement : 3 fine sand)
8.23 Rate as per item no 8.23 of SH : Cladding Work each 55 ₹40.85 ₹2,246.75
LABOUR
0111 Carpenter 1st class day 1.08 ₹897.00 ₹968.76
0112 Carpenter 2nd class day 0.8 ₹816.00 ₹652.80
0114 Beldar day 1.08 ₹736.00 ₹794.88
Priming coat
13.85.1 Rate as per item no 13.85.1 of SH : Finishing sqm 10 ₹70.35 ₹703.50
9999 Sundries & screws etc. L.S. 53.82 ₹2.27 ₹122.17

Rate build-up

TOTAL ₹17,910.06
Add 1 % Water charges on "W-A" ₹149.60
TOTAL ₹18,059.66
Add GST on "X-A" (multiplying factor 0.2127) ₹3,213.77
TOTAL ₹21,273.43
Add 15% CPOH on "Y-A" ₹2,748.48
TOTAL ₹24,021.91
Add Cess @ 1% on "Z-A" ₹210.72
Cost of 10 sqm. ₹24,232.63
Cost of 1 sqm. ₹2,423.26
Say ₹2,423.25