DSR 2023 · SH 8 · CLADDING WORK

CPWD DSR item 8.15 rate analysis

Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required.

Published rate₹714.40per kg
Rate analysis

Providing and fixing stainless steel cramps of required size and shape for anchoring stone wall lining to the backing or securing adjacent stones in stone wall lining in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases in stone and holes in walls wherever required.

DSR rate₹714.40per kg
Item code
8.15
Sub-head
SH 8 · CLADDING WORK
Unit
kg
Source row
1420

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one cramp of 0.934kg
MATERIAL
Stainless steel cramp
10 x 0.064 x 0.025 x 0.006 = 9.6 x 10^5
10 x 0.025 x 0.025 x 0.006 = 3.7 x 10^5
= 13.3 x 10^5
less hole 10 x 0.024 x 0.010 x 0.006
= 1.4 x 10^5
= 11.9 x 10^5 x 7850 = 0.934 kg
Add wastage @ 5% = 0.047kg.
Total = 0.981 kg.
7339 Stainless steel cramp kilogram 0.981 ₹313.00 ₹307.05
9977 CARRIAGE L.S. 3.9 ₹2.27 ₹8.85
Cement mortar 1:2 (1 cement : 2 coarse sand)
3.7 Rate as per Item Number 3.7 of SH: Mortars cum 0.001 ₹5,584.50 ₹5.58
9999 Labour for fixing in position L.S. 65 ₹2.27 ₹147.55

Rate build-up

TOTAL ₹469.03
Add 1 % Water charges on "W" ₹4.69
TOTAL ₹473.72
Add GST on "X" (multiplying factor 0.2127) ₹100.76
TOTAL ₹574.48
Add 15% CPOH on "Y" ₹86.17
TOTAL ₹660.65
Add Cess @ 1% on "Z" ₹6.61
Cost for 0.934 kg. ₹667.26
Cost per kg ₹714.41
Say ₹714.40