Rate analysis
Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : White sand stone - exposed face fine dressed with rough backing .
DSR rate₹7,278.20per sqm
70 mm thick
- Item code
- 8.14.3.1
- Sub-head
- SH 8 · CLADDING WORK
- Unit
- sqm
- Source row
- 593
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 sqm. | |||||
| MATERIAL | |||||
| Finished work = 70 cudm. Add wastage @ 33.3% = 23.33 cudm. Total = 93.33 cudm. | |||||
| 1161 | White sand stone block | 10 cudm | 9.333 | ₹205.00 | ₹1,913.27 |
| 2216 | Carriage of Stone blocks white & red sand stone & kota stone slab | tonne | 0.215 | ₹0.00 | ₹0.00 |
| @ 2.30kg/cudm | |||||
| 9999 | Extra for using white cement | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| Dressing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 1.35 | ₹816.00 | ₹1,101.60 |
| 0102 | Blacksmith 1st class | day | 0.032 | ₹897.00 | ₹28.70 |
| 0114 | Beldar | day | 0.224 | ₹736.00 | ₹164.86 |
| 0115 | Coolie | Day | 0.112 | ₹736.00 | ₹82.43 |
| 0100 | Bandhani | day | 0.224 | ₹816.00 | ₹182.78 |
| Fixing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.448 | ₹816.00 | ₹365.57 |
| 0100 | Bandhani | day | 0.336 | ₹816.00 | ₹274.18 |
| 0114 | Beldar | day | 0.336 | ₹736.00 | ₹247.30 |
| 0115 | Coolie | day | 0.336 | ₹736.00 | ₹247.30 |
| 0101 | Bhisti | day | 0.336 | ₹816.00 | ₹274.18 |
| 1237 | Cutting marble or sand stone slab upto 50 mm thick by mechanical device | metre | 4 | ₹10.00 | ₹40.00 |
| 9999 | Scaffolding | L.S. | 19.76 | ₹2.27 | ₹44.86 |
| Mortar for laying and pointing | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.018 | ₹4,881.95 | ₹87.88 |
Rate build-up
| TOTAL | ₹5,116.00 |
| Add 1 % Water charges on "W" | ₹51.16 |
| TOTAL | ₹5,167.16 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,099.05 |
| TOTAL | ₹6,266.21 |
| Add 15% CPOH on "Y" | ₹939.93 |
| TOTAL | ₹7,206.14 |
| Add Cess @ 1% on "Z" | ₹72.06 |
| Cost of 1 sqm. | ₹7,278.20 |
| Say | ₹7,278.20 |