Rate analysis
Stone work (machine cut edges) for wall lining etc. (veneer work) upto 10 metre height, backing filled with a grout of average 12 mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : (To be secured to the backing and the sides by means of cramps and pins which shall be paid for separately) : Red sand stone - exposed face fine dressed with rough backing.
DSR rate₹5,789.90per sqm
50 mm thick
- Item code
- 8.14.1.3
- Sub-head
- SH 8 · CLADDING WORK
- Unit
- sqm
- Source row
- 593
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 sqm. | |||||
| MATERIAL | |||||
| Finished work = 50 cudm+Add wastage @ 33.3% = 16.7 cudm. Total = 66.7 cudm. | |||||
| 1160 | Red sand stone block | 10 cudm | 6.67 | ₹130.00 | ₹867.10 |
| 2216 | Carriage of Stone blocks white & red sand stone & kota stone slab | tonne | 0.153 | ₹0.00 | ₹0.00 |
| @ 2.30kg/cudm | |||||
| 9999 | Extra for using white cement | L.S. | 26.91 | ₹2.27 | ₹61.09 |
| Dressing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class | day | 1.35 | ₹816.00 | ₹1,101.60 |
| 0102 | Blacksmith 1st class | day | 0.032 | ₹897.00 | ₹28.70 |
| 0114 | Beldar | day | 0.224 | ₹736.00 | ₹164.86 |
| 0115 | Coolie | day | 0.112 | ₹736.00 | ₹82.43 |
| 0100 | Bandhani | day | 0.224 | ₹816.00 | ₹182.78 |
| Fixing charges | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.448 | ₹816.00 | ₹365.57 |
| 0100 | Bandhani | day | 0.336 | ₹816.00 | ₹274.18 |
| 0114 | Beldar | day | 0.336 | ₹736.00 | ₹247.30 |
| 0115 | Coolie | day | 0.336 | ₹736.00 | ₹247.30 |
| 0101 | Bhisti | day | 0.336 | ₹816.00 | ₹274.18 |
| 1237 | Cutting marble or sand stone slab upto 50 mm thick by mechanical device | metre | 4 | ₹10.00 | ₹40.00 |
| 9999 | Scaffolding | L.S. | 19.76 | ₹2.27 | ₹44.86 |
| Mortar for laying and pointing | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.018 | ₹4,881.95 | ₹87.88 |
Rate build-up
| TOTAL | ₹4,069.83 |
| Add 1 % Water charges on "W" | ₹40.70 |
| TOTAL | ₹4,110.53 |
| Add GST on "X" (multiplying factor 0.2127) | ₹874.31 |
| TOTAL | ₹4,984.84 |
| Add 15% CPOH on "Y" | ₹747.73 |
| TOTAL | ₹5,732.57 |
| Add Cess @ 1% on "Z" | ₹57.33 |
| Cost of 1 sqm. | ₹5,789.90 |
| Say | ₹5,789.90 |