DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.31 rate analysis

Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long

Published rate₹6,788.85DSR 2023
Rate analysis

Providing and fixing red sand stone brackets 55x22.5x45 cm sunk and moulded including providing and fixing with 4 Nos gun metal cramp 25x6 mm 30 cm long

DSR rate₹6,788.85as per item analysis
Item code
7.31
Sub-head
SH 7 · STONE WORK
Unit
See analysis
Source row
1415

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 bracket
Quantity of stone for 1 bracket
1 x 55 x 22.5 x 45cm = 0.056cum or 56 cudm.
Red sand stone = 56 cudm.
Add wastage 10% = 5.6 cudm.
Total = 61.6 cudm.
1160 Red sand stone block 10 cudm 6.16 ₹130.00 ₹800.80
2216 Carriage of Stone blocks white & red sand stone & kota stone slab @ 2.3kg/ cudm. tonne 0.14 ₹0.00 ₹0.00
Dressing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 1.7926 ₹816.00 ₹1,462.76
0102 Blacksmith 1st class day 0.037 ₹897.00 ₹33.19
0114 Beldar day 0.271 ₹736.00 ₹199.46
0115 Coolie day 0.1355 ₹736.00 ₹99.73
0100 Bandhani day 0.271 ₹816.00 ₹221.14
0373 Cramp Gun metal 25x6x300 mm each 4 ₹88.00 ₹352.00
Fixing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.2464 ₹816.00 ₹201.06
0102 Blacksmith 1st class day 0.0336 ₹897.00 ₹30.14
0114 Beldar day 0.1232 ₹736.00 ₹90.68
0115 Coolie day 0.1232 ₹736.00 ₹90.68
0100 Bandhani day 0.1232 ₹816.00 ₹100.53
0101 Bhisti day 0.1232 ₹816.00 ₹100.53
9999 Scaffolding L.S. 15.29 ₹2.27 ₹34.71
9999 Mortar for laying and pointing L.S. 45.14 ₹2.27 ₹102.47
Extra labour for ornamental finish :
0126 Mason (for ornamental stone work) 1st class day 0.95 ₹897.00 ₹852.15

Rate build-up

TOTAL ₹4,772.03
Add 1 % Water charges on "W" ₹47.72
TOTAL ₹4,819.75
Add GST on "X" (multiplying factor 0.2127) ₹1,025.16
TOTAL ₹5,844.91
Add 15% CPOH on "Y" ₹876.74
TOTAL ₹6,721.65
Add Cess @ 1% on "Z" ₹67.22
Cost for 1 Bracket ₹6,788.87
Say ₹6,788.85