CPWD DSR item 7.26 rate analysis

Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases.

Published rate₹54.55DSR 2023
Rate analysis

Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as per design in cement mortar 1:2 (1 cement : 2 coarse sand), including making the necessary chases.

DSR rate₹54.55as per item analysis
Item code
7.26
Sub-head
SH 7 · STONE WORK
Unit
See analysis
Source row
1225

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for one dowel
9999 Cost of stone including carriage L.S. 9.1 ₹2.27 ₹20.66
9999 Labour for dressing dowel cutting chase and fixing etc. L.S. 5.33 ₹2.27 ₹12.10
Cement mortar 1:2 (1 cement : 2 coarse sand)
3.7 Rate as per Item Number 3.7 of SH: Mortars cum 0.001 ₹5,584.50 ₹5.58

Rate build-up

TOTAL ₹38.34
Add 1 % Water charges on "W" ₹0.38
TOTAL ₹38.72
Add GST on "X" (multiplying factor 0.2127) ₹8.24
TOTAL ₹46.96
Add 15% CPOH on "Y" ₹7.04
TOTAL ₹54.00
Add Cess @ 1% on "Z" ₹0.54
Cost of each dowel ₹54.54
Say ₹54.55

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook