DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.19 rate analysis

Extra for additional cost of centering for arches exceeding 6m span including all strutting, bolting, wedging etc. and removal (area of soffit to be measured).

Published rate₹608.15per sqm of soffit area
Rate analysis

Extra for additional cost of centering for arches exceeding 6m span including all strutting, bolting, wedging etc. and removal (area of soffit to be measured).

DSR rate₹608.15per sqm of soffit area
Item code
7.19
Sub-head
SH 7 · STONE WORK
Unit
sqm of soffit area
Source row
1013

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 333.1 sqm
Centering and shuttering for arches and carved surface exceeding 6m in span (an average of 8m)
Radius R = 5m
2R-2 = 4+4
tan -¹ (4/3)=53.28°
2x53.28=106°
Surface area =10x2x3.142x5x3.6x106/360=333.1 sqm.
Arc=9.25m
MATERIAL
Tie-2x8x0.18x0.05 =0.144cum
Struts-2x2.5x0.1x0.1 =0.050cum.
Struts-2x1.77x0.1x0.1=0.035cum.
Ribs-6x1.54x0.23x0.1=0.213cum.
Struts-2x1.72x0.1x0.1=0.034cum.
Total=0.476cum.
For four such frames =0.476x4 = 1.904 cum.
laggings-75x3.6x0.125x0.075=2.531cum.
Tie-2x3.6x0.225x0.038=0.062cum.
Brace-3x2x2.14x0.225x0.038=0.110
Brace-3x4x3.8x0.225x0.038=0.390
Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
Vertical post-4x4x3.6x0.15x0.15=1.296
Total = 7.103cum. Quantity for 10 Nos. = 7.103x10 = 71.03 cum
Qty taken as 1/8th of qty for cost of using once = 71.03/8 = 8.879 cum (8879 cudm)
1197 Second class kail wood in scantling 10 cudm 887.9 ₹260.00 ₹2,30,854.00
2204 Carriage of Timber cum 8.879 ₹0.00 ₹0.00
Fittings:
3 way straps 50mmx10mm = 32 Nos.
32 no. @0.50m each = 16m
Straps-50mmx10mm = 8 Nos. @0.25m
each = 2m
Total = 18m
For 10 Nos. = 10x18m, wt @ 3.9kg/m = 702 kg. = 7.02q
Qty taken l/8th of qty for cost using once = 7.02/8 = 0.878 qtl.
1225 Mild steel flat strap fitting quintal 0.878 ₹4,120.00 ₹3,617.36
Bolts 160 Nos. 254 mm long 16mm dia.- 10x160x.254xl .58=642.1 kg=6.42q.
Qty taken 1/8th of qty for cost using once = 6.42/8 = 0.802 qtl
1034 Bolts and nuts upto 300 mm in length quintal 0.802 ₹5,200.00 ₹4,170.40
Carriage of steel
Qty taken 1/8th of qty for cost using once = 0.878+0.802=1.680 q = 0.168 tonne
2302 Carriage of G.I.sheet and accessories tonne 0.168 ₹0.00 ₹0.00
LABOUR
0112 Carpenter 2nd class day 280 ₹816.00 ₹2,28,480.00
0114 Beldar day 240 ₹736.00 ₹1,76,640.00
9999 Sundries L.S. 1,345.5 ₹2.27 ₹3,054.29
Less Cost of shuttering etc. for an arch exceeding 6 m span i.e. for an average of 8 m span
5.9.9 Rate as per item no 5.9.9 of SH : Reinforced cement concrete work sqm -333.1 ₹2,154.35 -₹7,17,613.99

Rate build-up

TOTAL -₹70,797.94
Add 1 % Water charges on "W-A" ₹6,468.16
TOTAL -₹64,329.78
Add GST on "X-A" (multiplying factor 0.2127) ₹1,38,953.55
TOTAL ₹74,623.77
Add 15% CPOH on "Y-A" ₹1,18,835.66
TOTAL ₹1,93,459.43
Add Cess @ 1% on "Z-A" ₹9,110.73
Cost of 333.1sqm. ₹2,02,570.16
Cost per sqm of soffit area ₹608.14
Say ₹608.15

Use this rate in the interactive workbook