DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.35.1 rate analysis

Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139, class designation 10 average compressive strength in super structure above plinth level up to floor V level in : Cement mortar 1:4 (1 cement : 4 coarse sand)

Published rate₹9,793.75per cum
Rate analysis

Brick work with modular calcium silicate bricks machine moulded conforming to IS:4139, class designation 10 average compressive strength in super structure above plinth level up to floor V level in :

DSR rate₹9,793.75per cum

Cement mortar 1:4 (1 cement : 4 coarse sand)

Item code
6.35.1
Sub-head
SH 6 · MASONRY WORK
Unit
cum
Source row
1287

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7738 Calcium Silicate Bricks machine moulded confirming to I.S. 4139 - 1989 1000 Nos 0.487 ₹5,700.00 ₹2,775.90
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.22 ₹4,211.70 ₹926.57
2201 Carriage of Bricks 1000 Nos 0.487 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
LABOUR
0123 Mason 1st class day 0.47 ₹897.00 ₹421.59
0124 Mason 2nd class day 0.47 ₹816.00 ₹383.52
0115 Coolie day 1.8 ₹736.00 ₹1,324.80
0101 Bhisti day 0.2 ₹816.00 ₹163.20
9999 Scaffolding L.S. 22.36 ₹2.27 ₹50.76
Extra labour element required for lifting of materials above floor two level upto floor V level (0.75 x 1.5 = 1.13)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹6,884.22
Add 1 % Water charges on "W" ₹68.84
TOTAL ₹6,953.06
Add GST on "X" (multiplying factor 0.2127) ₹1,478.92
TOTAL ₹8,431.98
Add 15% CPOH on "Y" ₹1,264.80
TOTAL ₹9,696.78
Add Cess @ 1% on "Z" ₹96.97
Cost per cum. ₹9,793.75
Say ₹9,793.75

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook