Brick work with common burnt clay machine moulded F.P.S. (non modular) bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand). From ground level upto plinth level

Published rate₹7,581.15per Cum
Rate analysis

Brick work with common burnt clay machine moulded F.P.S. (non modular) bricks of class designation 12.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand).

DSR rate₹7,581.15per Cum

From ground level upto plinth level

Item code
6.29.1
Sub-head
SH 6 · MASONRY WORK
Unit
Cum
Source row
1009

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
7903 Machine moulded common burnt clay FPS (non modular) bricks of class designation 12.5 1000 Nos 0.494 ₹5,300.00 ₹2,618.20
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.25 ₹3,541.40 ₹885.35
9999 Sundries i/c steel / wooden strips for making grooves L.S. 16.38 ₹2.27 ₹37.18
LABOUR
0123 Mason 1st class day 0.36 ₹897.00 ₹322.92
0124 Mason 2nd class day 0.36 ₹816.00 ₹293.76
0115 Coolie day 1.37 ₹736.00 ₹1,008.32
0101 Bhisti day 0.2 ₹816.00 ₹163.20

Rate build-up

TOTAL ₹5,328.93
Add 1 % Water charges on "W" ₹53.29
TOTAL ₹5,382.22
Add GST on "X" (multiplying factor 0.2127) ₹1,144.80
TOTAL ₹6,527.02
Add 15% CPOH on "Y" ₹979.05
TOTAL ₹7,506.07
Add Cess @ 1% on "Z" ₹75.06
Cost of 1 Cum. ₹7,581.13
Say ₹7,581.15