Rate analysis
Brick work with common burnt clay modular bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand).
DSR rate₹8,312.90per Cum
Above plinth level upto floor V level
- Item code
- 6.27.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 902
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 7900 | Modular common burnt clay bricks of class designation 7.5 | 1000 Nos | 0.487 | ₹4,500.00 | ₹2,191.50 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.487 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.22 | ₹3,541.40 | ₹779.11 |
| 9999 | Sundries i/c steel / wooden strips for making grooves | L.S. | 16.38 | ₹2.27 | ₹37.18 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.44 | ₹897.00 | ₹394.68 |
| 0124 | Mason 2nd class | day | 0.44 | ₹816.00 | ₹359.04 |
| 0115 | Coolie | day | 1.43 | ₹736.00 | ₹1,052.48 |
| 0101 | Bhisti | day | 0.18 | ₹816.00 | ₹146.88 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
| 9999 | Sundries | L.S. | 22.36 | ₹2.27 | ₹50.76 |
Rate build-up
| TOTAL | ₹5,843.31 |
| Add 1 % Water charges on "W" | ₹58.43 |
| TOTAL | ₹5,901.74 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,255.30 |
| TOTAL | ₹7,157.04 |
| Add 15% CPOH on "Y" | ₹1,073.56 |
| TOTAL | ₹8,230.60 |
| Add Cess @ 1% on "Z" | ₹82.31 |
| Cost of 1 Cum. | ₹8,312.91 |
| Say | ₹8,312.90 |