Rate analysis
Brick work with common burnt clay selected F.P.S. (non modular) bricks of class designation 7.5 in exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete in cement mortar 1:6 (1 cement : 6 coarse sand)
DSR rate₹9,439.75per cum
Above plinth level upto floor V level
- Item code
- 6.26.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- cum
- Source row
- 845
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.494 | ₹4,724.00 | ₹2,333.66 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.494 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.25 | ₹3,541.40 | ₹885.35 |
| 9999 | Sundries including steel/wooden strips for making grooves. | L.S. | 16.38 | ₹2.27 | ₹37.18 |
| LABOUR | |||||
| For selection of bricks | |||||
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 0123 | Mason 1st class | day | 0.46 | ₹897.00 | ₹412.62 |
| 0124 | Mason 2nd class | day | 0.46 | ₹816.00 | ₹375.36 |
| 0115 | Coolie | day | 1.6 | ₹736.00 | ₹1,177.60 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
| 9999 | Sundries | L.S. | 22.36 | ₹2.27 | ₹50.76 |
Rate build-up
| TOTAL | ₹6,635.41 |
| Add 1 % Water charges on "W" | ₹66.35 |
| TOTAL | ₹6,701.76 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,425.46 |
| TOTAL | ₹8,127.22 |
| Add 15% CPOH on "Y" | ₹1,219.08 |
| TOTAL | ₹9,346.30 |
| Add Cess @ 1% on "Z" | ₹93.46 |
| Cost per cum. | ₹9,439.76 |
| Say | ₹9,439.75 |