Rate analysis
Extra for laying brick work in or under foul position.
DSR rate₹467.55as per item analysis
- Item code
- 6.25
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 826
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| Extra labour due to slow progress- | |||||
| 0123 | Mason 1st class | day | 0.02 | ₹897.00 | ₹17.94 |
| 0124 | Mason 2nd class | day | 0.02 | ₹816.00 | ₹16.32 |
| 0114 | Beldar | day | 0.25 | ₹736.00 | ₹184.00 |
| 0115 | Coolie | day | 0.15 | ₹736.00 | ₹110.40 |
Rate build-up
| TOTAL | ₹328.66 |
| Add 1 % Water charges on "W" | ₹3.29 |
| TOTAL | ₹331.95 |
| Add GST on "X" (multiplying factor 0.2127) | ₹70.61 |
| TOTAL | ₹402.56 |
| Add 15% CPOH on "Y" | ₹60.38 |
| TOTAL | ₹462.94 |
| Add Cess @ 1% on "Z" | ₹4.63 |
| Cost for 1 cum. | ₹467.57 |
| Say | ₹467.55 |