DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.23 rate analysis

Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand).

Published rate₹711.50DSR 2023
Rate analysis

Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand).

DSR rate₹711.50as per item analysis
Item code
6.23
Sub-head
SH 6 · MASONRY WORK
Unit
See analysis
Source row
786

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1sqm. of Honey comb
brick works-
MATERIAL
Brick work, with bricks of class designation 75, in cement mortar 1:4 (1 Cement : 4 Coarse sand) in superstructure
1 m x 1 x 0.143 m x 4.5/7.5 = 0.069 cum
6.4.1 Rate as per item No 6.4.1 of SH :- Brick work. cum 0.069 ₹9,344.35 ₹644.76
9999 Extra for delay due to fine work L.S. 20.67 ₹2.27 ₹46.92

Rate build-up

TOTAL ₹691.68
Add 1 % Water charges on "W-A" ₹0.47
TOTAL ₹692.15
Add GST on "X-A" (multiplying factor 0.2127) ₹10.08
TOTAL ₹702.23
Add 15% CPOH on "Y-A" ₹8.62
TOTAL ₹710.85
Add Cess @ 1% on "Z-A" ₹0.66
Cost for 1 sqm. ₹711.51
Say ₹711.50