Rate analysis
Honey-comb brick work 10 / 11.4 cm thick with common burnt clay bricks of class designation 7.5 in super structure above plinth level upto floor V level with cement mortar 1:4 (1 cement : 4 coarse sand).
DSR rate₹711.50as per item analysis
- Item code
- 6.23
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 786
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1sqm. of Honey comb | |||||
| brick works- | |||||
| MATERIAL | |||||
| Brick work, with bricks of class designation 75, in cement mortar 1:4 (1 Cement : 4 Coarse sand) in superstructure | |||||
| 1 m x 1 x 0.143 m x 4.5/7.5 = 0.069 cum | |||||
| 6.4.1 | Rate as per item No 6.4.1 of SH :- Brick work. | cum | 0.069 | ₹9,344.35 | ₹644.76 |
| 9999 | Extra for delay due to fine work | L.S. | 20.67 | ₹2.27 | ₹46.92 |
Rate build-up
| TOTAL | ₹691.68 |
| Add 1 % Water charges on "W-A" | ₹0.47 |
| TOTAL | ₹692.15 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹10.08 |
| TOTAL | ₹702.23 |
| Add 15% CPOH on "Y-A" | ₹8.62 |
| TOTAL | ₹710.85 |
| Add Cess @ 1% on "Z-A" | ₹0.66 |
| Cost for 1 sqm. | ₹711.51 |