Rate analysis
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in:
DSR rate₹7,132.25per Cum
Cement mortar 1:6 (1 cement : 6 coarse sand)
- Item code
- 6.1.2
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- Cum
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.494 | ₹4,724.00 | ₹2,333.66 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.494 | ₹0.00 | ₹0.00 |
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) (Rate as per item No 3.11) | |||||
| 3.11 | Rate as per Item No.3.11 of SH: Mortar | cum | 0.25 | ₹3,541.40 | ₹885.35 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.36 | ₹897.00 | ₹322.92 |
| 0124 | Mason 2nd class | day | 0.36 | ₹816.00 | ₹293.76 |
| 0115 | Coolie | day | 1.37 | ₹736.00 | ₹1,008.32 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
Rate build-up
| TOTAL | ₹5,013.41 |
| Add 1 % Water charges on "W" | ₹50.13 |
| TOTAL | ₹5,063.54 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,077.01 |
| TOTAL | ₹6,140.55 |
| Add 15% CPOH on "Y" | ₹921.08 |
| TOTAL | ₹7,061.63 |
| Add Cess @ 1% on "Z" | ₹70.62 |
| Cost of 1 Cum. | ₹7,132.25 |
| Say | ₹7,132.25 |