Rate analysis
Brick work in gauged arches in superstructure above plinth level and upto floor five level in cement mortar 1:3 (1 cement : 3 coarse sand) including centering and shuttering complete, for span up to 6 meters with common burnt clay F.P.S. (non modular) bricks of class designation 7.5.
DSR rate₹19,066.10as per item analysis
- Item code
- 6.1
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 353
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.538 | ₹4,724.00 | ₹2,541.51 |
| Cement mortar 1:3 | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.25 | ₹4,881.95 | ₹1,220.49 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.538 | ₹0.00 | ₹0.00 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
| Centring and shuttering (Area same as in item No. 6.9) | |||||
| 5.9.9 | Rate as per item no 5.9.9 of SH : Reinforced cement concrete work | sqm | 2.25 | ₹2,154.35 | ₹4,847.29 |
| 9999 | Scaffolding | L.S. | 18.85 | ₹2.27 | ₹42.79 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 1.13 | ₹897.00 | ₹1,013.61 |
| 0124 | Mason 2nd class | day | 1.13 | ₹816.00 | ₹922.08 |
| 0115 | Coolie | day | 4.42 | ₹736.00 | ₹3,253.12 |
| 0101 | Bhisti | day | 0.2 | ₹816.00 | ₹163.20 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
Rate build-up
| TOTAL | ₹14,841.97 |
| Add 1 % Water charges on "W-A" | ₹99.95 |
| TOTAL | ₹14,941.92 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹2,147.13 |
| TOTAL | ₹17,089.05 |
| Add 15% CPOH on "Y-A" | ₹1,836.26 |
| TOTAL | ₹18,925.31 |
| Add Cess @ 1% on "Z-A" | ₹140.78 |
| Cost for 1 cum. | ₹19,066.09 |
| Say | ₹19,066.10 |