DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.7 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Stairs, (excluding landings) except spiral-staircases

Published rate₹764.95per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹764.95per sqm

Stairs, (excluding landings) except spiral-staircases

Item code
5.9.7
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 57.9 sqm.
Details of 10 Nos. staircase, 3.40m clear span including 1m landing.
MATERIAL
(i) Cost of plank 38mm (2nd class kail wood)
Waist= 10x2.69x1.30 = 35.0sqm.
Side shuttering of steps and side of waist-Steps
10x8x1.30x0.15 = 15.6 sqm.
Face of landing
10x1x1.30x0.15 = 2.0 sqm.
Side of waist
10x2.69x0.13 = 3.5 sqm.
Side of steps-
10x8x0.50x0.30x0.15 = 1.80sqm.
Total = 57.9 sqm.
Wastage 5% = 2.9sqm.
Total = 60.8 sq.
Cubical content- 60.8x0.038 = 2.31 cum = 2310 dm³
Qty taken for cost using once = 2310/8= 288.75 cudm
1198 Second class kail wood in planks 10 cudm 28.875 ₹260.00 ₹7,507.50
(ii) Batten 100mm x 75mm
10x4x1.30x0.100x0.075=0.39 cum = 390 dm³
Qty taken for cost using once = 390/8 = 48.75 cudm
1197 Second class kail wood in scantling 10 cudm 4.875 ₹260.00 ₹1,267.50
10x2x4x0.80 = 64.0m
Qty taken for cost using once = 64.0/8 = 8.0 m
0302 Safeda ballies 125 mm diameter metre 8 ₹44.00 ₹352.00
Planks = 2.31 cum.
Battens = 0.39 cum.
Ballies 64x3.142/4x(0.125)² = 0.79cum.
Total = 3.49 cum.
Qty taken for cost using once = 3.49/8 = 0.436 cum
2204 Carriage of Timber cum 0.436 ₹0.00 ₹0.00
LABOUR
For assembling, erection, dismantling and cleaning
0112 Carpenter 2nd class day 17.5 ₹816.00 ₹14,280.00
0114 Beldar day 10 ₹736.00 ₹7,360.00
9999 Sundries L.S. 161.2 ₹2.27 ₹365.92

Rate build-up

TOTAL ₹31,132.92
Add 1 % Water charges on "W" ₹311.33
TOTAL ₹31,444.25
Add GST on "X-A" (multiplying factor 0.2127) ₹6,688.19
TOTAL ₹38,132.44
Add 15% CPOH on "Y" ₹5,719.87
TOTAL ₹43,852.31
Add Cess @ 1% on "Z" ₹438.52
Cost of 57.9 sqm. ₹44,290.83
Cost per sqm. ₹764.95
Say ₹764.95