DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.5 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers

Published rate₹736.40per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹736.40per sqm

Lintels, beams, plinth beams, girders, bressumers and cantilevers

Item code
5.9.5
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Consider 10 beam of 6 m clear span, 0.50 m deep 0.30 m wide and height 3.5 m from floor
Cubical contents
10x6.60x0.5x0.3 = 9.9 cum
10x1x1.30x6.00 = 78 sqm
MATERIAL
Assuming shuttering will become unserviceable after use of 40 times
Add maintenance charges @ 10% of cost of material
Less salvage value of material after full use @ 25% of cost of material
1. Steel plates for side and bottom
(plate size 1.20 x 0.50m)
Angle 40x40x5mm
2x1.20 = 2.40 m
3x0.50 = 1.50 m
3.90 m @ 3.00 kg/m = 11.70 kg
sheet 1.6 mm thick
1.20m x 0.50 m = 0.60 sqm.
0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.
Weight of one plate = 19.23 kg.
Add for wastage @ 5% = 0.96 kg.
Total = 20.19 kg.
Total weight of all plates=
10x3x5x20.19 = 3028.5 kg
Qty taken for cost of using once = 13028.5x0.85/40 = 64.356 kg.
10.1 Rate as per item no.10.1 S.H. steel work kg 64.356 ₹117.35 ₹7,552.18
7343 Adjustable telescopic prop 3 m (2.02-3.75 m) each 1.275 ₹1,051.00 ₹1,340.03
Qty taken for cost of using once =10x6x0.85/40 = 1.275 m
7344 Beam clamp 300-380 mm (450-1070 mm) each set 1.063 ₹375.00 ₹398.63
Qty taken for cost of using once = 10x5x0.85/40 = 1.063 m
9999 (iv) Assembly nut & bolts etc. L.S. 221 ₹2.27 ₹501.67
Qty taken for cost of using once = 10x1040x0.85/40 = 221
9977 Carriage L.S. 780 ₹2.27 ₹1,770.60
LABOUR
0116 Fitter (grade 1) day 12.5 ₹897.00 ₹11,212.50
0114 Beldar day 25 ₹736.00 ₹18,400.00
9999 Shuttering oil L.S. 390 ₹2.27 ₹885.30
9999 Sundries, paper tape etc. L.S. 246.1 ₹2.27 ₹558.65

Rate build-up

TOTAL ₹42,619.56
Add 1 % Water charges on "W-A" ₹350.67
TOTAL ₹42,970.23
Add GST on "X-A" (multiplying factor 0.2127) ₹7,533.42
TOTAL ₹50,503.65
Add 15% CPOH on "Y-A" ₹6,442.72
TOTAL ₹56,946.37
Add Cess @ 1% on "Z-A" ₹493.94
Cost for 78 sqm. ₹57,440.31
Cost per sqm. ₹736.41
Say ₹736.40

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook