DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.9.19 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for Weather shade, Chajjas, corbels etc., including edges

Published rate₹951.10per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form for

DSR rate₹951.10per sqm

Weather shade, Chajjas, corbels etc., including edges

Item code
5.9.19
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
sqm
Source row
594

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Nos. weather shade
Area of centring and shuttering = 9.54 sqm
For a weather shade over a window of size 1.5mx1.2m
Size of weather shade 1.80x0.45m
Thickness at front = 0.05m
Thickness at fixed edge = 0.07m
Area in contact with concrete Bottom
10x1x0.45x1.80 = 8.10
10x1x0.05x1.80 = 0.90
10x2x0.45x0.06 = 0.54
Total = 9.54 sqm.
MATERIAL
Assuming that the timber will become unserviceable after being used 8 times.
1198 Second class kail wood in planks 10 cudm 5.3 ₹260.00 ₹1,378.00
(i) Planking 38mm thick.
Bottom 10x1x1.876x0.488 = 9.15 sqm.
10x1x1.876x0.05 = 0.94 sqm.
10x2x0.45x0.06 = 0.54 sqm.
Total = 10.63 sqm.
Add 5% wastage = 0.53 sqm.
Total = 11.16 sqm.
Cubic contains
11.16x0.038 = 0.424 cum = 424 cudm
Qty taken for cost using once = 424/8 = 53.00 cudm
1197 Second class kail wood in scantling 10 cudm 1.5 ₹260.00 ₹390.00
(ii) Battens-
10x2x0.60x0.075x0.10 = 0.09
Ends with bearing center
10x1x0.45x0.075x0.10 = 0.03
Total = 0.12 cum = 120 cudm
Qty taken for cost using once =120/8=15 cudm
2447 Hollock ballies 125 mm diameter metre 5.513 ₹37.00 ₹203.98
(iii) Ballies 125mm dia.
10x2x2.1 = 42m
Wastage 5% = 2.1m
Total = 44.1 m
Qty taken for cost using once = 44.1/8 = 5.513 m
Carriage:
2204 Carriage of Timber cum 0.136 ₹0.00 ₹0.00
Plank = 0.424 cum.
Battens = 0.12 cum.
Ballies
44.1x3.142x(0.125)²/4 = 0.54 cum.
Total = 1.084 cum
Qty taken for cost using once = 1.084/8 = 0.136 cum
LABOUR
Labour for assembling, erection, dismantling & cleaning
0112 Carpenter 2nd class day 3 ₹816.00 ₹2,448.00
0114 Beldar day 2.5 ₹736.00 ₹1,840.00
9999 Sundries L.S. 52 ₹2.27 ₹118.04

Rate build-up

TOTAL ₹6,378.02
Add 1 % Water charges on "W" ₹63.78
TOTAL ₹6,441.80
Add GST on "X" (multiplying factor 0.2127) ₹1,370.17
TOTAL ₹7,811.97
Add 15% CPOH on "Y" ₹1,171.80
TOTAL ₹8,983.77
Add Cess @ 1% on "Z" ₹89.84
Cost for 9.54 sqm. ₹9,073.61
Cost of 1 sqm. ₹951.11
Say ₹951.10