DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.47.3 rate analysis

Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineer-in-charge. The frame shall be measured in running metre correct to two places of decimal. Door frame 85 mmx60 mm

Published rate₹727.30per metre
Rate analysis

Providing and fixing in position factory made precast RCC M-40 door and window frame fixing with hold fast embedded in 1:3:6 concrete block , having excellent smooth finish as per IS: 6523 with reinforcement of 3 Nos, 6 mm dia main bars tied with 3 mm M.S stirrups placed @ 200 mm C/C and 6 numbers high strength polymer blocks of required size for fixing hinges including providing 6 no specially designed M.S. galvanised sleeves for accomodating 6 mm dia fully threaded bolts for fixing hold fast on vertical members, providing suitable arrangement for recieving sliding door bolts and tower bolt etc. all complete, as per the direction of Engineer-in-charge. The frame shall be measured in running metre correct to two places of decimal.

DSR rate₹727.30per metre

Door frame 85 mmx60 mm

Item code
5.47.3
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
metre
Source row
4040

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 52 metre (10 Nos door frame)
MATERIAL
5.33.1.4 RCC M40 Rate as per Item No.5.33.1.4 of SH: REINFORCED CEMENT CONCRETE cum 0.27 ₹9,957.65 ₹2,688.57
Extra for scatter and smaller work @25 % i.e. Px0.25 ₹672.14
1005 Twisted steel/ deformed bars quintal 0.324 ₹5,550.00 ₹1,798.20
0596 Bright finished or black enameled mild steel butt hinges 75x47x1.70 mm 10 Nos 6 ₹63.00 ₹378.00
4.3.3 Centering and shuttering Rate as per Item No.4.3.3 of SH: CONCRETE WORK sqm 10.7 ₹961.30 ₹10,285.91
14.2.1 Fixing chowkhat Rate as per Item No.14.2.1 of SH: REPAIRS TO BUILDINGS each 10 ₹1,782.55 ₹17,825.50
9999 Sundries L.S. 1,006.7 ₹2.27 ₹2,285.21

Rate build-up

TOTAL ₹35,933.53
Add 1 % Water charges on "W-A-P-R" ₹44.61
TOTAL ₹35,978.14
Add GST on "X-A-P-R" (multiplying factor 0.2127) ₹958.43
TOTAL ₹36,936.57
Add 15% CPOH on "Y-A-P-R" ₹819.67
TOTAL ₹37,756.24
Add Cess @ 1% on "Z-A-P-R" ₹62.84
Cost of 52 metre ₹37,819.08
Cost of 1 metre ₹727.29
Say ₹727.30