Rate analysis
Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or part thereof.
DSR rate₹355.65as per item analysis
- Item code
- 5.38
- Sub-head
- SH 5 · REINFORCED CEMENT CONCRETE
- Unit
- See analysis
- Source row
- 3658
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| MATERIAL | |||||
| 0009 | Pumping charges of concrete including Hire charges of pump, piping work & accessories etc | cum | 1 | ₹250.00 | ₹250.00 |
Rate build-up
| TOTAL | ₹250.00 |
| Add 1 % Water charges on "W" | ₹2.50 |
| TOTAL | ₹252.50 |
| Add GST on "X" (multiplying factor 0.2127) | ₹53.71 |
| TOTAL | ₹306.21 |
| Add 15% CPOH on "Y" | ₹45.93 |
| TOTAL | ₹352.14 |
| Add Cess @ 1% on "Z" | ₹3.52 |
| Cost for 1 cum | ₹355.66 |
| Say | ₹355.65 |