DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.31 rate analysis

Extra for laying reinforced cement concrete in or under water and/ or liquid mud, including cost of pumping or bailing out water and removing slush etc., complete. Note For Item No. 5.31:- The quantity will be calculated by multiplying the depth measured from the subsoil water level up to the centre of gravity of the R.C.C. under subsoil water with the quantity of R.C.C. in cubic metre executed under subsoil water. The depth of centre of gravity shall be reckoned correct to 0.1 m. 0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored. No extra payment shall be made for placing reinforcement or centering & shuttering under sub - soil water conditions.

Published rate₹1,098.80DSR 2023
Rate analysis

Extra for laying reinforced cement concrete in or under water and/ or liquid mud, including cost of pumping or bailing out water and removing slush etc., complete. Note For Item No. 5.31:- The quantity will be calculated by multiplying the depth measured from the subsoil water level up to the centre of gravity of the R.C.C. under subsoil water with the quantity of R.C.C. in cubic metre executed under subsoil water. The depth of centre of gravity shall be reckoned correct to 0.1 m. 0.05 m or more shall be taken as 0.1 m and less than 0.05 m ignored. No extra payment shall be made for placing reinforcement or centering & shuttering under sub - soil water conditions.

DSR rate₹1,098.80as per item analysis
Item code
5.31
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
3097

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 4.2 cum per 1 m depth (14 cum per 0.3m depth)
Quantity of concrete = 14 cum.
Analysis same as per item number 4.15
pumping hours = 3 hrs. or 0.375 day.
0011 Hire charges of Pumpset of capacity 4000 litres/hour. for cleaning slush day 0.375 ₹800.00 ₹300.00
0114 Beldar day 4 ₹736.00 ₹2,944.00

Rate build-up

TOTAL ₹3,244.00
Add 1 % Water charges on "W" ₹32.44
TOTAL ₹3,276.44
Add GST on "X" (multiplying factor 0.2127) ₹696.90
TOTAL ₹3,973.34
Add 15% CPOH on "Y" ₹596.00
TOTAL ₹4,569.34
Add Cess @ 1% on "Z" ₹45.69
Cost of 4.2cum per 1 metre depth ₹4,615.03
Cost of cum per metre depth ₹1,098.82
Say ₹1,098.80