DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.26 rate analysis

Providing and filling in position, blown bitumen in expansion joints.

Published rate₹74,854.65DSR 2023
Rate analysis

Providing and filling in position, blown bitumen in expansion joints.

DSR rate₹74,854.65as per item analysis
Item code
5.26
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
See analysis
Source row
2833

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a joint of 300m length, 2.5cm width and 15cm depth = 1.125 cum
Cubical content of joint-
300x0.025x0.150=1.125 cum.
MATERIAL
Bitumen 85/25 @ 1050kg per cum.
1.125x1050kg = 1181.25kg
Add wastage @ 5% = 59.06 kg.
= 1240.31 = 1.240 tonne
0313 Blown type petroleum bitumen of penetration 85/25 of approved quality tonne 1.24 ₹38,250.00 ₹47,430.00
2211 Carriage of Tar/ bitumen tonne 1.24 ₹0.00 ₹0.00
0370 Coal (steam) quintal 2.48 ₹500.00 ₹1,240.00
For heating of bitumen @ 2.0 quintal per tonne of bitumen.
1.240x2.0=2.48q=0.248t
2200 Carriage of steam coal tonne 0.248 ₹0.00 ₹0.00
LABOUR
Labour for heating, mixing and filling-
0123 Mason 1st class day 2.52 ₹897.00 ₹2,260.44
0124 Mason 2nd class day 2.52 ₹816.00 ₹2,056.32
0114 Beldar day 8.06 ₹736.00 ₹5,932.16
9999 Sundries L.S. 121.16 ₹2.27 ₹275.03

Rate build-up

TOTAL ₹59,193.95
Add 1 % Water charges on "W" ₹591.94
TOTAL ₹59,785.89
Add GST on "X" (multiplying factor 0.2127) ₹12,716.46
TOTAL ₹72,502.35
Add 15% CPOH on "Y" ₹10,875.35
TOTAL ₹83,377.70
Add Cess @ 1% on "Z" ₹833.78
Cost for 1.125 cum ₹84,211.48
cost for 1.00cum ₹74,854.65
Say ₹74,854.65