DSR 2023 · SH 5 · REINFORCED CEMENT CONCRETE

CPWD DSR item 5.17A rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins individually or forming box louvers setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%).

Published rate₹11,872.55per cum
Rate analysis

Providing, transporting, hoisting and fixing above plinth level up to floor five level precast reinforced cement concrete in vertical & horizontal fins individually or forming box louvers setting in cement mortar 1:2 (1 cement : 2 coarse sand), including the cost of required centering, shuttering but excluding the cost of reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand incuding manufactured sand derived from Recycled Concrete Aggregate (RCA) upto 20% : 3 graded stone aggregate 20 mm nominal size including Recycled Concrete Aggregate (RCA) upto 20%).

DSR rate₹11,872.55per cum
Item code
5.17A
Sub-head
SH 5 · REINFORCED CEMENT CONCRETE
Unit
cum
Source row
2140

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 Nos. of 4 RCC vertical fins 4m high at lm centre to centre with two horizontal fins, all projecting 60cm from face of wall and 5cm thick cubical contents = 10x 0.66 cum = 6.6 cum
MATERIAL:
Cement concrete 1:1.5:3
Sub AR-1 Rate as per sub AR-1 (Ref item no 4.1.2) cum 6.6 ₹8,170.05 ₹53,922.33
Centering and shuttering
4.3.1 Rate as per Item Number 4.3.1 of SH: Concrete work sqm 25.6 ₹392.15 ₹10,039.04
Extra labour for lifting from FL II upto Floor Level V (Coolie = 6.6x0.75x1.50=7.4)
0115 Coolie day 7.4 ₹736.00 ₹5,446.40
LABOUR:
Extra labour for laying cement concrete in RCC work due to delay etc.
0114 Beldar day 0.66 ₹736.00 ₹485.76
0101 Bhisti day 1.32 ₹816.00 ₹1,077.12
0123 Mason 1st class day 0.264 ₹897.00 ₹236.81
0124 Mason 2nd class day 0.264 ₹816.00 ₹215.42
0128 Mate day 0.264 ₹816.00 ₹215.42
9999 Cement mortar 1:3 for fixing L.S. 179.4 ₹2.27 ₹407.24
9999 Labour for hoisting, Transporting and setting L.S. 717.6 ₹2.27 ₹1,628.95
9999 Sundries L.S. 179.4 ₹2.27 ₹407.24

Rate build-up

Total ₹74,081.73
Add 1 % Water charges on "W-A" ₹101.20
TOTAL ₹74,182.93
Add GST on "X-A" (multiplying factor 0.2127) ₹2,174.13
TOTAL ₹76,357.06
Add 15% CPOH on "Y-A" ₹1,859.35
TOTAL ₹78,216.41
Add Cess @ 1% on "Z-A" ₹142.55
Cost of 6.6 cum ₹78,358.96
Cost of 1 cum ₹11,872.57
Say ₹11,872.55