DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.3.3 rate analysis

Centering and shuttering including strutting, propping etc. and removal of form work for : Columns, piers, abutments, pillars, posts and struts

Published rate₹961.30per sqm
Rate analysis

Centering and shuttering including strutting, propping etc. and removal of form work for :

DSR rate₹961.30per sqm

Columns, piers, abutments, pillars, posts and struts

Item code
4.3.3
Sub-head
SH 4 · CONCRETE WORK
Unit
sqm
Source row
908

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for 4.5sqm
Size of column 450x450mm and 2.5m high
Area of contact = 4x0.45x2.5 = 4.5 sqm.
MATERIAL
Assuming shuttering will become unserviceable after use of 40 times
Add maintenance charges @ 10% of cost of material
Less salvage value of material after full use @ 25% of cost of material
7331 Wall form panel 1250x450 mm each 0.17 ₹900.00 ₹153.00
Qty taken for cost of using once = 8x0.85/40 = 0.17
7332 Corner angle 45x45x5 mm 2.50 m long each 0.085 ₹275.00 ₹23.38
Qty taken for cost of using once =4x0.85/40 = 0.085
7333 Column clamp 450x1070 mm each 0.1063 ₹1,020.00 ₹108.43
Qty taken for cost of using once =5x0.85/40 = 0.1063
7334 Prop 2 m ( 2-3.5m) each 0.085 ₹690.00 ₹58.65
Qty taken for cost of using once =4x0.85/40 = 0.085
9999 Assembly nut & bolt L.S. 27.62 ₹2.27 ₹62.70
9977 CARRIAGE L.S. 52 ₹2.27 ₹118.04
LABOUR
0116 Fitter (grade 1) day 1 ₹897.00 ₹897.00
0114 Beldar day 2 ₹736.00 ₹1,472.00
9999 Shuttering oil L.S. 39 ₹2.27 ₹88.53
9977 Carriage L.S. 26 ₹2.27 ₹59.02

Rate build-up

TOTAL ₹3,040.75
Add 1 % Water charges on "W" ₹30.41
TOTAL ₹3,071.16
Add GST on "X" (multiplying factor 0.2127) ₹653.24
TOTAL ₹3,724.40
Add 15% CPOH on "Y" ₹558.66
TOTAL ₹4,283.06
Add Cess @ 1% on "Z" ₹42.83
Cost for 4.5 sqm. ₹4,325.89
Cost per sqm. ₹961.31
Say ₹961.30

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook