DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.20A.2.1 rate analysis

Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources and using recycled concrete aggregate (RCA) as coarse aggregate and fine aggregate within the permissible utilization, Portland Pozzolana / Ordinary Portland/Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement. . All works above plinth and upto floor V level Concrete of M10 grade with minimum cement content of 220 kg /cum. (Note: The permissible utilization of Recycled Concrete Aggregate (RCA) as coarse aggregate and fine aggregate is 100% each).

Published rate₹8,291.75per 1.00 cum
Rate analysis

Providing and laying in position ready mixed or site batched design mix cement concrete for plain cement concrete work; using coarse aggregate and fine aggregate derived from natural sources and using recycled concrete aggregate (RCA) as coarse aggregate and fine aggregate within the permissible utilization, Portland Pozzolana / Ordinary Portland/Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering and finishing as per direction of the engineer-in-charge; for the following grades of concrete.

DSR rate₹8,291.75per 1.00 cum

Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the minimum specified cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.

. All works above plinth and upto floor V level

Concrete of M10 grade with minimum cement content of 220 kg /cum.

(Note: The permissible utilization of Recycled Concrete Aggregate (RCA) as coarse aggregate and fine aggregate is 100% each).

Item code
4.20A.2.1
Sub-head
SH 4 · CONCRETE WORK
Unit
1.00 cum
Source row
2116

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 cum
MATERIAL
0279 Recycled Concrete Aggregate (RCA)) 20 mm nominal size cum 0.89 ₹957.00 ₹851.73
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.89 ₹0.00 ₹0.00
0278 Fine aggregate derivered from recycled concrete aggregate (RCA) cum 0.47 ₹957.00 ₹449.79
2203 Carriage of fine aggregate derivered from recycled concrete aggregate (RCA) cum 0.47 ₹0.00 ₹0.00
0367 Ordinary/Pozzolana/Slag Cement tonne 0.22 ₹5,156.00 ₹1,134.32
2209 Carriage of Cement tonne 0.22 ₹0.00 ₹0.00
7318 Plasticizer / super plasticizer kilogram 1.1 ₹30.00 ₹33.00
Production cost, pumping to respective floors and laying in position
0004 Production cost of concrete by batch mix plant / ready mixed plant. cum 1 ₹450.00 ₹450.00
0009 Pumping charges of concrete including carriage for all leads and hire charges of pump, piping work & accessories etc. cum 1 ₹250.00 ₹250.00
Labour for pouring, consolidating & curing
0155 Mason (average) day 0.17 ₹857.00 ₹145.69
0114 Beldar day 2 ₹736.00 ₹1,472.00
0101 Bhisti day 0.9 ₹816.00 ₹734.40
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Sundries L.S. 13 ₹2.27 ₹29.51
Extra cost of additional piping work and accessories etc. upto floor V level = 100% of P ₹250.00

Rate build-up

TOTAL ₹5,828.44
Add 1 % Water charges on "W" ₹58.28
TOTAL ₹5,886.72
Add GST on "X" (multiplying factor 0.2127) ₹1,252.11
TOTAL ₹7,138.83
Add 15% CPOH on "Y" ₹1,070.82
TOTAL ₹8,209.65
Add Cess @ 1% on "Z" ₹82.10
Cost per 1.00 cum ₹8,291.75
Say ₹8,291.75

Use this rate in the interactive workbook