DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.20.2.3 rate analysis

All works above plinth and upto floor V level Concrete of M20 grade with minimum cement content of 270 kg /cum

Published rate₹9,568.25per 1.00 cum
Rate analysis

All works above plinth and upto floor V level

DSR rate₹9,568.25per 1.00 cum

Concrete of M20 grade with minimum cement content of 270 kg /cum

Item code
4.20.2.3
Sub-head
SH 4 · CONCRETE WORK
Unit
1.00 cum
Source row
1975

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 cum
MATERIAL
0293 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 ₹1,400.00 ₹910.00
(0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 ₹1,425.00 ₹342.00
2206 Carriage of Stone aggregate 40 mm nominal size and above cum 0.65 ₹0.00 ₹0.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.24 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 0.47 ₹1,450.00 ₹681.50
2203 Carriage of Coarse sand cum 0.47 ₹0.00 ₹0.00
0367 Ordinary/Pozzolana/Slag Cement tonne 0.27 ₹5,156.00 ₹1,392.12
2209 Carriage of Cement tonne 0.27 ₹0.00 ₹0.00
7318 Plasticizer / super plasticizer kilogram 1.35 ₹30.00 ₹40.50
Production cost, pumping to respective floors and laying in position
0004 Production cost of concrete by batch mix plant / ready mixed plant. cum 1 ₹450.00 ₹450.00
0009 Pumping charges of concrete including carriage for all leads and hire charges of pump, piping work & accessories etc. cum 1 ₹250.00 ₹250.00
Labour for pouring, consolidating & curing
0155 Mason (average) day 0.17 ₹857.00 ₹145.69
0114 Beldar day 2 ₹736.00 ₹1,472.00
0101 Bhisti day 0.9 ₹816.00 ₹734.40
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Sundries L.S. 13 ₹2.27 ₹29.51
Extra cost of additional piping work and accessories etc. upto floor V level = 100% of P ₹250.00

Rate build-up

TOTAL ₹6,725.72
Add 1 % Water charges on "W" ₹67.26
TOTAL ₹6,792.98
Add GST on "X" (multiplying factor 0.2127) ₹1,444.87
TOTAL ₹8,237.85
Add 15% CPOH on "Y" ₹1,235.68
TOTAL ₹9,473.53
Add Cess @ 1% on "Z" ₹94.74
Cost per 1.00 cum ₹9,568.27
Say ₹9,568.25