DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.20.2.1 rate analysis

All works above plinth and upto floor V level Concrete of M10 grade with minimum cement content of 220 kg /cum

Published rate₹9,190.80per 1.00 cum
Rate analysis

All works above plinth and upto floor V level

DSR rate₹9,190.80per 1.00 cum

Concrete of M10 grade with minimum cement content of 220 kg /cum

Item code
4.20.2.1
Sub-head
SH 4 · CONCRETE WORK
Unit
1.00 cum
Source row
1975

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1.00 cum
MATERIAL
0293 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 ₹1,400.00 ₹910.00
(0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)
0295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 ₹1,425.00 ₹342.00
2206 Carriage of Stone aggregate 40 mm nominal size and above cum 0.65 ₹0.00 ₹0.00
2202 Carriage of Stone aggregate below 40 mm nominal size cum 0.24 ₹0.00 ₹0.00
0982 Coarse sand (zone III) cum 0.47 ₹1,450.00 ₹681.50
2203 Carriage of Coarse sand cum 0.47 ₹0.00 ₹0.00
0367 Ordinary/Pozzolana/Slag Cement tonne 0.22 ₹5,156.00 ₹1,134.32
2209 Carriage of Cement tonne 0.22 ₹0.00 ₹0.00
7318 Plasticizer / super plasticizer kilogram 1.1 ₹30.00 ₹33.00
Production cost, pumping to respective floors and laying in position
0004 Production cost of concrete by batch mix plant / ready mixed plant. cum 1 ₹450.00 ₹450.00
0009 Pumping charges of concrete including carriage for all leads and hire charges of pump, piping work & accessories etc. cum 1 ₹250.00 ₹250.00
Labour for pouring, consolidating & curing
0155 Mason (average) day 0.17 ₹857.00 ₹145.69
0114 Beldar day 2 ₹736.00 ₹1,472.00
0101 Bhisti day 0.9 ₹816.00 ₹734.40
0012 Vibrator(Needle type 40mm) day 0.07 ₹400.00 ₹28.00
9999 Sundries L.S. 13 ₹2.27 ₹29.51
Extra cost of additional piping work and accessories etc. upto floor V level = 100% of P ₹250.00

Rate build-up

TOTAL ₹6,460.42
Add 1 % Water charges on "W" ₹64.60
TOTAL ₹6,525.02
Add GST on "X" (multiplying factor 0.2127) ₹1,387.87
TOTAL ₹7,912.89
Add 15% CPOH on "Y" ₹1,186.93
TOTAL ₹9,099.82
Add Cess @ 1% on "Z" ₹91.00
Cost per 1.00 cum ₹9,190.82
Say ₹9,190.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook