Rate analysis
All works upto plinth level :
DSR rate₹8,986.15per 1.00 cum
Concrete of M15 grade with minimum cement content of 240 kg /cum Details of cost for 1.00 cum MATERIAL
- Item code
- 4.20.1.2
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- 1.00 cum
- Source row
- 1842
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| 0293 | Stone Aggregate (Single size) : 40 mm nominal size | cum | 0.65 | ₹1,400.00 | ₹910.00 |
| (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum) | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.24 | ₹1,425.00 | ₹342.00 |
| 2206 | Carriage of Stone aggregate 40 mm nominal size and above | cum | 0.65 | ₹0.00 | ₹0.00 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.24 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.47 | ₹1,450.00 | ₹681.50 |
| 2203 | Carriage of Coarse sand | cum | 0.47 | ₹0.00 | ₹0.00 |
| 0367 | Ordinary/Pozzolana/Slag Cement | tonne | 0.24 | ₹5,156.00 | ₹1,237.44 |
| 2209 | Carriage of Cement | tonne | 0.24 | ₹0.00 | ₹0.00 |
| 7318 | Plasticizer / super plasticizer | kilogram | 1.2 | ₹30.00 | ₹36.00 |
| Production cost, pumping to respective floors and laying in position | |||||
| 0004 | Production cost of concrete by batch mix plant / ready mixed plant. | cum | 1 | ₹450.00 | ₹450.00 |
| 0009 | Pumping charges of concrete including carriage for all leads and hire charges of pump, piping work & accessories etc. | cum | 1 | ₹250.00 | ₹250.00 |
| — | Labour for pouring, consolidating & curing | — | — | — | ₹0.00 |
| 0155 | Mason (average) | day | 0.17 | ₹857.00 | ₹145.69 |
| 0114 | Beldar | day | 2 | ₹736.00 | ₹1,472.00 |
| 0101 | Bhisti | day | 0.9 | ₹816.00 | ₹734.40 |
| 0012 | Vibrator(Needle type 40mm) | day | 0.07 | ₹400.00 | ₹28.00 |
| 9999 | Sundries | L.S. | 13 | ₹2.27 | ₹29.51 |
Rate build-up
| TOTAL | ₹6,316.54 |
| Add 1 % Water charges on "W" | ₹63.17 |
| TOTAL | ₹6,379.71 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,356.96 |
| TOTAL | ₹7,736.67 |
| Add 15% CPOH on "Y" | ₹1,160.50 |
| TOTAL | ₹8,897.17 |
| Add Cess @ 1% on "Z" | ₹88.97 |
| Cost per 1.00 cum | ₹8,986.14 |
| Say | ₹8,986.15 |