Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:
1:5:10 (1 cement : 5 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 10 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA))
Published rate₹6,912.45per cum
Rate analysis
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:
DSR rate₹6,912.45per cum
1:5:10 (1 cement : 5 manufactured sand derived from Recycled Concrete Aggregate (RCA) : 10 graded stone aggregate 40 mm nominal size Recycled Aggregate (RA))
Item code
4.2.8A
Sub-head
SH 4 · CONCRETE WORK
Unit
cum
Source row
594
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 1 cum.
MATERIAL
0282
Recycled Aggregate (RA) 40 mm nominal size
cum
0.65
₹390.00
₹253.50
0283
Recycled Aggregate (RA) 20 mm nominal size
cum
0.24
₹420.00
₹100.80
2206
Carriage of Recycled Aggregate 40 mm nominal size and above
cum
0.65
₹0.00
₹0.00
2202
Carriage of Recycled Aggregate below 40 mm nominal size
cum
0.24
₹0.00
₹0.00
0278
Manufactured sand derived from Recycled Concrete Aggregate (RCA)
cum
0.47
₹957.00
₹449.79
2203
Carriage of manufactured sand
cum
0.47
₹0.00
₹0.00
0367
Portland Cement
tonne
0.13
₹5,156.00
₹670.28
2209
Carriage of Cement
tonne
0.13
₹0.00
₹0.00
LABOUR
0114
Beldar
day
0.9
₹736.00
₹662.40
0115
Coolie
day
0.78
₹736.00
₹574.08
0101
Bhisti
day
0.7
₹816.00
₹571.20
0123
Mason (brick layer) 1st class
day
0.1
₹897.00
₹89.70
0002
Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper
day
0.07
₹900.00
₹63.00
0012
Vibrator(Needle type 40mm)
day
0.07
₹400.00
₹28.00
9999
Scaffolding
L.S.
114.4
₹2.27
₹259.69
9999
Sundries
L.S.
14.3
₹2.27
₹32.46
(Extra labour for lifting material upto floor V level = 0.75 x 2.0 = 1.50)
0115
Coolie
day
1.5
₹736.00
₹1,104.00
Rate build-up
TOTAL
₹4,858.90
Add 1 % Water charges on "W"
₹48.59
TOTAL
₹4,907.49
Add GST on "X" (multiplying factor 0.2127)
₹1,043.82
TOTAL
₹5,951.31
Add 15% CPOH on "Y"
₹892.70
TOTAL
₹6,844.01
Add Cess @ 1% on "Z"
₹68.44
Cost of 1 cum.
₹6,912.45
Say
₹6,912.45
Use this rate in the interactive workbook
Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.