DSR 2023 · SH 4 · CONCRETE WORK

CPWD DSR item 4.15 rate analysis

Extra for laying concrete in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete.

Published rate₹1,098.80DSR 2023
Rate analysis

Extra for laying concrete in or under water and/or liquid mud including cost of pumping or bailing out water and removing slush etc. complete.

DSR rate₹1,098.80as per item analysis
Item code
4.15
Sub-head
SH 4 · CONCRETE WORK
Unit
See analysis
Source row
1661

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 4.2 cum per 1 m depth (14 cum per 0.3m depth)
Quantity of concrete = 14 cum. pumping hours = 3 hrs. or 0.375 day.
0011 Hire charges of Pumpset of capacity 4000 litres/hour. day 0.375 ₹800.00 ₹300.00
0114 Beldar day 4 ₹736.00 ₹2,944.00
for cleaning slush

Rate build-up

TOTAL ₹3,244.00
Add 1 % Water charges on "W" ₹32.44
TOTAL ₹3,276.44
Add GST on "X" (multiplying factor 0.2127) ₹696.90
TOTAL ₹3,973.34
Add 15% CPOH on "Y" ₹596.00
TOTAL ₹4,569.34
Add Cess @ 1% on "Z" ₹45.69
Cost of 4.2cum per 1 metre depth ₹4,615.03
Cost of cum per metre depth ₹1,098.82
Say ₹1,098.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook