Rate analysis
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
DSR rate₹7,178.75per cum
1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources)
- Item code
- 4.1.6
- Sub-head
- SH 4 · CONCRETE WORK
- Unit
- cum
- Source row
- 4
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum. | |||||
| MATERIAL | |||||
| 0293 | Stone Aggregate (Single size) : 40 mm nominal size | cum | 0.65 | ₹1,400.00 | ₹910.00 |
| (0.70 cum - 7.5% for voids i.e. 0.05 =0.65 cum) | |||||
| 0295 | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.24 | ₹1,425.00 | ₹342.00 |
| 2206 | Carriage of Stone aggregate 40 mm nominal size and above | cum | 0.65 | ₹0.00 | ₹0.00 |
| 2202 | Carriage of Stone aggregate below 40 mm nominal size | cum | 0.24 | ₹0.00 | ₹0.00 |
| 0982 | Coarse sand (zone III) | cum | 0.47 | ₹1,450.00 | ₹681.50 |
| 2203 | Carriage of Coarse sand | cum | 0.47 | ₹0.00 | ₹0.00 |
| 0367 | Portland Cement (0.15674 cum) | tonne | 0.22 | ₹5,156.00 | ₹1,134.32 |
| 2209 | Carriage of Cement | tonne | 0.22 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0155 | Mason (average) | day | 0.1 | ₹857.00 | ₹85.70 |
| 0114 | Beldar | day | 1.63 | ₹736.00 | ₹1,199.68 |
| 0101 | Bhisti | day | 0.7 | ₹816.00 | ₹571.20 |
| 0002 | Hire charges of Concrete Mixer 0.25 to 0.40 cum with hooper | day | 0.07 | ₹900.00 | ₹63.00 |
| 0012 | Vibrator(Needle type 40mm) | day | 0.07 | ₹400.00 | ₹28.00 |
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹5,046.09 |
| Add 1 % Water charges on "W" | ₹50.46 |
| TOTAL | ₹5,096.55 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,084.04 |
| TOTAL | ₹6,180.59 |
| Add 15% CPOH on "Y" | ₹927.09 |
| TOTAL | ₹7,107.68 |
| Add Cess @ 1% on "Z" | ₹71.08 |
| Cost of 1 cum. | ₹7,178.76 |
| Say | ₹7,178.75 |